The median barrier on I-5 between 47th Avenue SW and S 48th Street had been in place for decades and was deteriorating.
This project replaced 2,000 individual sections of concrete median barrier, each weighing about 5,000 pounds.
Crews started construction in early June 2008 and completed the project in July 2008.
 | Improves Safety
Replacing the concrete median barrier increases safety by reducing the risk of cross-over collisions.
|
Partnerships & Cooperation
The construction contract was awarded to Petersen Brothers, Inc. of Sumner.
Funding
This project is funded through the following sources:
- Federal Highway Safety Improvement Program - $1,250,000
- Total Funding Available From All Sources - $1, 250,000
Contact Us
For more information, contact the project office:
Howard Diep, Project Engineer
Lakewood Project Engineer Office
11203 Bridgeport Way SW
Lakewood, WA 98499
or
P.O. Box 47440
Olympia, WA 98504-7440
Phone: 1-888-220-2984
Email: DiepH@wsdot.wa.gov