November 2009
- Construction began in mid-July.
- Lanes and ramps in south King County will be closed during construction. Check the Construction Update Report for upcoming closures.
WSDOT is repaving the northbound I-5 on- and off-ramps at S. 188th Street, the northbound I-5 off-ramp at Southcenter Parkway, all the ramps at S. 272nd Street and S. 272nd Street under I-5. Crews also will replace old signs, improve lighting, bring guardrail up to current safety standards and improve sidewalk accessibility.
Why is WSDOT
making improvements to I-5 ramps in south King County?
The pavement at several freeway on- and off-ramps is old and deteriorating, causing cracks and potholes. Many of the signs don't meet reflectivity standards and require extra lighting. The guardrail also does not meet current safety standards.
The End Result
The end result of this project will be smoother pavement at the on- and off-ramps, improved lighting, more visible signage and improved sidewalk accessibility.
Project Benefits
- Safety: New pavement and signs, improved guardrail and lighting, and new sidewalk ramps will improve safety for drivers and pedestrians.
What is the project timeline?
- February 2009: Project awarded to Tucci & Sons, Inc.
- July 2009: Construction began
- September 2009: Expected completion
Financial Information
- Pre-existing funds: $3.1 million
- Total funding from all sources: $3.1 million
How can I get more information?
Contact:
Mark Sawyer
Construction Project Engineer
425-649-4429
SawyerM@wsdot.wa.gov
Mike Murphy
WSDOT Communications
206-440-4699
MurphyM@wsdot.wa.gov
back to top