I-405 Kirkland Nickel Stage 1 Project - April 2006

Bridge work at NE 116th -- Nighttime
Crews demolish a portion of the I-405 bridge over NE 116th Street in Kirkland. The bridge will be demolished and constructed in phases. The new bridge will accommodate an additional lane of traffic in each direction. 

Work on the NE116th Bridge
I-405 remained open during bridge demolition. Crews began work at 11 p.m. on Friday April 21st and completed the work by 4 p.m. Sunday the 23rd, 12 hours earlier than expected.

Closure at NE 116th Street
NE 116th Street was closed where it crosses under I-405.  A signed detour provided access around the closed area.   

Crews working near the exit of NE 124th
Crews prepare the approaches for the new, widened bridge.  The bridge is scheduled for completion in 2007.