I-5 Tukwila to Pierce County Line HOV Lane – Stage 3 |
King County |
Good |
Fair |
Completed seven days ahead of schedule and is expected to come in about 8% over the engineer’s estimates of $28 million. |
|
SR 500 Thurston Way |
Vancouver |
Good |
Good |
This is the state's first design build project. It was completed on schedule and on budget ($22.7 million). |
|
SR 16, Sprague Avenue to Snake Lake |
Tacoma |
Poor |
Poor |
Deficiencies in the plan required redesign work and extended the project construction schedule by about 90 working days. The project is expected to come in about 12% over engineer’s estimates of $15.2 million. |
|
I-5 Widening, 93rd Avenue to Maytown |
Thurston County |
Good |
Good |
Completed on time and approximately 6% under the $8.5 million engineer’s estimate. |
|
SR 529, Steamboat Slough Bridge Rehabilitation |
Everett |
Good |
Mixed |
Completed ahead of schedule and 58% over the $8 million engineer’s estimates due principally to revised traffic mitigation plans and a larger incentive payment earned by the contractor for an early project finish. |
|
SR 303, Phase 2 Safety Improvement |
Kitsap County |
Fair |
Good |
Work is expected to finish slightly over schedule and is expected to be 3% under engineers estimates of $4.1 million. |
|
US 2, Hewitt Avenue Trestle |
Snohomish County |
Good |
Mixed |
Completed work requiring 24 hour lane closure 10.5 days ahead of schedule. Project costs were 79% over the engineer's estimate of $4.09 million. This was due in part to an increase of 30% over the contractor's bid amount for revised traffic plans and early completion objectives. |
|
US 2, Deer Rd. to Westwood Rd. Paving |
North of Spokane |
Good |
Good |
Completed on time and is expected to come in approximately 20% under engineer’s estimates of $2.8 million. |
|
SR 500, Vancouver - Burnt Bridge Creek to Andresen Road |
Vancouver |
Good |
Good |
Completed on time and is anticipated to come in 9% - 10% under engineer’s estimate of $2 million. |
|
US 12, Cowiche Creek to I-82 Paving |
Yakima County |
Good |
Good |
Completed on time and 19% under the $1.9 million engineer’s estimate. |
|
I-90, Harvard Rd. Interchange- Westbound Ramp Revisions |
Liberty Lake, Spokane County |
Good |
Good |
Completed on time and is anticipated to come in at about 22% under engineer’s estimate of $1,692,122. |
|
I-5 Olive to Boylston Electrical Upgrade |
Seattle |
Good |
Poor |
Completed on time but about 20% over the $1.6 million engineer’s estimate. |
|
I-5 Northgate Bridge Deck Repair |
North Seattle |
Good |
Mixed |
Completed three days ahead of schedule at about 20% over the $1,292,460 engineer’s estimate and also over the bid. |
|
SR 127, Church Hill Rd to Dusty (SR 26) Paving |
Whitman County |
Good |
Good |
Completed on time and is anticipated to come in at about 15% under the $1.3 million engineer’s estimate. |
|
I-5 Ramp Paving – South Tacoma To Fife |
Pierce County |
Good |
Good |
Completed on time and is expected to come in about 10% under engineer’s estimate of $1.06 million. |
|
SR 507, Centralia – I-5 to Old Skookumchuck River Bridge |
Lewis County |
Good |
Good |
Completed on time and about 24% under the $800,697 engineer’s estimates. |
|
SR 543, Boblett Street Signalization |
Blaine |
Good |
Good |
Completed on time and about 21% under engineer’s estimates of $714,442. |
|
SR 153, Carlton Bridge Repair |
Okanogan County |
Good |
Fair |
Completed ahead of schedule and 8% over the $484,508 engineer’s estimate. |
|
US 97, Tonasket-Bonapart Creek Bridge Deck |
Okanogan County |
Good |
Good |
Completed on time and approximately 0.7% under engineer’s estimate of $153,568. |
|
I-82, Ellensburg/Selah Area Variable Message Signs |
Yakima County |
Good |
Mixed |
Completed on time and approximately 13% over the $119,374 engineer’s estimates. |
|
SR 500, NE 124th Ave. Intersection – Safety Improvements |
Clark County |
Good |
Good |
Completed on schedule and approximately .2% under the engineer’s estimate of $86,664. |
|
|
|
Kingston Ferry Terminal, Phase 2 Dolphin Replacements |
Kitsap County |
Good |
Good |
Completed ahead of schedule and 12% under engineer’s estimates of $1.7 million. |