Overview
We replaced one floating and two fixed timber dolphins with three steel fixed dolphins. Dolphins are offshore structures that help guide the ferry. View a diagram of ferry terminal components.
 | Improves Safety
This project preserves the landing aids for slip #1 by installing new structures with a 50-year life.
|
 | Protects Environment
Removing the creosote timber dolphins and installing steel dolphins improves the environment for salmon.
|
Partnerships & Cooperation
Contractor American Construction completed this work.
Funding
Construction costs were budgeted at $2.9 million.