This roadway preservation projects seals 105 miles of roadway in the following sections:
SR 23/Steptoe to Sprague (MP 0-44)
SR 23/Sprague to Lord’s Creek (MP 44-54)
SR 231/Sprague to US 2 @ Reardan (MP 0-28)
SR 231/Reardan to Fisher Road (MP 31-40)
SR 902/Interstate 90 to Lakeland Village (MP 0-4)
SR 904/Tyler to Cheney (MP 0-9)
Why is WSDOT
chip sealing these sections of highways?
The pavement through these sections is deteriorating and was scheduled for surface restoration before the underlying road structure is damaged.
The End Result
A fresh layer of Bituminous Surface Treatment that extends the usable life of the underlying roadway.
Project Benefits
- Extends the pavement life
- Provides a smoother ride
- Improves drainage
- Reduces maintenance
What is the project timeline?
This project will be built and completed during the 2013 construction season.
Financial Information
Project signage will reflect the cost of construction engineering, project bid award and sales tax.
| Financial Data for PIN 600023L |
| Funding Source |
Amount ($ in thousands) |
| 2003 Gas Tax (Nickel Funding) |
$0 |
| 2005 Gas Tax (TPA) |
$0 |
| Pre-Existing Funds (PEF) |
$207 |
| Total |
$207 |
|
How can I get more information?
Contact:
Chad Simonson, Project Engineer
2714 N. Mayfair
Spokane, WA 99207
(509)324-6250
simonsc@wsdot.wa.gov