Design Memorandum
TO: All Design Staff
FROM: Bijan Khaleghi
DATE: November 4, 2014
SUBJECT: Archiving Design and Check Calculations, Design Files, and S&E Files
This design memorandum defines WSDOT policy for archiving design and check calculations, design files, and S&E files. Archiving of Contract Plans and as-built plans will be addressed in a subsequent policy memorandum. read more....
If you have any questions regarding this issue, please contact Scott Sargent at 705-7753, David Lemcke at 705-7211, or Bijan Khaleghi at 705-7181.
cc: Mark Gaines, Bridge Construction – 47354
Craig Boone, Bridge and Structures – 47340
|