The following Washington State Department of Transportation projects are expected to have some travel impacts. Motorists are encouraged to use caution when traveling in these areas and remember to "give 'em a brake" in construction zones.
Get updates for your county:
PLEASE NOTE: Most activities are subject to good weather conditions and work plans are subject to weather-related adjustments.
Counties: Clallam | Grays Harbor | Jefferson | Kitsap | Mason | Pierce | Thurston
The following construction and maintenance activities are scheduled for the week of April 8 - 14, 2013:
CONSTRUCTION
US 101 Shore Rd to Kitchen-Dick Rd Widening, Shore Rd
Jerry Moore, 360-565-0622
TIME/DAYS: 7:30 a.m. to 4:30 p.m. Monday-Friday, April 8-12.
DESCRIPTION: This project widens US 101 in Clallam County from Shore Road to Kitchen-Dick Road.
LOCATION: Both directions of US 101, Shore to Kitchen Dick Road, mileposts 260 to 265.
EXPECT: Contractor's work will be limited to the area of McDonald Creek and Pierson Rd. Expect short term traffic shifts throughout the project for relocation of utilities.
MAINTENANCE
No maintenance activities that will impact traffic are scheduled this week.
top
CONSTRUCTION
No construction activities that will impact traffic are scheduled this week.
MAINTENANCE
US 12, Elma to Montesano
Randy Moody, 360-538-8530
TIME/DAYS: 7 a.m. to 4:30 p.m. Monday, April 8.
DESCRIPTION: Mobile sweeping operation.
LOCATION: Both directions of US 12, Elma to Montesano, mileposts 9.5 to 21.
EXPECT: Mobile, right-lane closure.
US 12, Elma to Mud Bay
Randy Moody, 360-538-8530
TIME/DAYS: 7 a.m. to 4:30 p.m. Tuesday, April 9 - Thursday, April 11.
DESCRIPTION: Mobile sweeping operation.
LOCATION: Both directions of US 12, Elma to Mud Bay, mileposts 0 to 21.
EXPECT: Mobile, right-lane closure.
US 12, One mile east of Gibson Creek Bridge
Randy Moody, 360-538-8530
TIME/DAYS: 1 to 4 p.m. Wednesday, April 4.
DESCRIPTION: Tree removal.
LOCATION: Both directions, US 12, one mile east of Gibson Creek Bridge, milepost 30.7 to 30.9.
EXPECT: One-way, alternating traffic.
US 12, Comcast Crossing, Elma Area
Pete Townsend, 360-570-6743
TIME/DAYS: 10 p.m. to 5 a.m. Tuesday, April 9.
DESCRIPTION: Utility work.
LOCATION: Both directions, US 12, Elma Area, milepost 20.12.
EXPECT: Rolling slowdown in both directions, lasting 10 minutes.
US 12, Between Aberdeen and Montesano
Tony Kilmer, 360-357-2763
TIME/DAYS: 9:00 a.m. to 2:30 p.m. Tuesday, April 9 to Thursday, April 11.
DESCRIPTION: Bridge maintenance.
LOCATION: Both directions, US 12, Wynoochee River, mileposts 8 to 9.
EXPECT: Single lane closures.
US 12, East of Brady
Randy Moody, 360-538-8530
TIME/DAYS: 7:30 a.m. to 4:30 p.m. Tuesday, April 9.
DESCRIPTION: Guardrail repair.
LOCATION: Both directions, US 12, east of Brady, mileposts 15.8 to 15.9.
EXPECT: Alternating single lane closures in both directions.
US 101, Near Pacific and Grays Harbor county lines
Randy Moody, 360-538-8530
TIME/DAYS: 7 a.m. to noon, Wednesday, April 10.
DESCRIPTION: Grading work.
LOCATION: Both directions, US 101, Rock Crusher Hill, mileposts 72.6 to 72.65.
EXPECT: One-way, alternating traffic.
US 101, Near Pacific and Grays Harbor county lines
Randy Moody, 360-538-8530
TIME/DAYS: 7:30 a.m. to 4 p.m. Thursday, April 11.
DESCRIPTION: Tree removal.
LOCATION: Both directions, US 101, north of North River Bridge, mileposts 74.6 to 74.8.
EXPECT: One-way, alternating traffic.
SR 105, Aberdeen to Grayland
Randy Moody, 360-538-8532
TIME/DAYS: 7 a.m. to 4 p.m. Monday, April 8 to Thursday, April 11.
DESCRIPTION: Vegetation management.
LOCATION: Both directions, SR 105, Aberdeen to Grayland, mileposts 25 to 47.
EXPECT: Mobile, single-lane and shoulder closures.
SR 107, One mile south of Montesano
Randy Moody, 360-538-8530
TIME/DAYS: 1 to 4 p.m. Monday, April 8.
DESCRIPTION: Tree removal.
LOCATION: Both directions, SR 107, 1 mile south of Montesano, mileposts 6.5 to 6.6.
EXPECT: One-way alternating traffic.
SR 109, Hoquiam to Taholah
Randy Moody, 360-538-8532
TIME/DAYS: 7 a.m. to 4 p.m Monday, April 8 to Thursday, April 11
DESCRIPTION: Sign washing.
LOCATION: Both directions, SR 109, Hoquiam to Taholah, mileposts 1 to 40.4.
EXPECT: Mobile, single-lane and shoulder closures.
top
CONSTRUCTION
No construction activities scheduled this week that will impact traffic.
MAINTENANCE
US 101, Fulton Creek
Duke Stryker, 360-874-3050
TIME/DAYS: 8:30 a.m. to 3:30 p.m. Monday, April 8.
DESCRIPTION: Vegetation management.
LOCATION: Both directions, US 101, Fulton Creek, mileposts 314 to 315.
EXPECT: One-way, alternating traffic.
top
CONSTRUCTION
No construction activities that will impact traffic are scheduled this week.
MAINTENANCE
No maintenance activities that will impact traffic are scheduled this week.
top
CONSTRUCTION
No construction activities that will affect traffic are scheduled this week.
MAINTENANCE
SR 3, at SR 302 intersection
Duke Stryker, 360-874-3050
TIME/DAYS: 8 a.m. to 3 p.m. Wednesday, April 10.
DESCRIPTION: Roadside maintenance.
LOCATION: Both directions, SR 3, at SR 302 intersection, mileposts 23 to 24.
EXPECT: One-way, alternating traffic.
SR 3, Shelton
Duke Stryker, 360-874-3050
TIME/DAYS: 8 a.m. to 3 p.m Thursday, April 11.
DESCRIPTION: Sweeping operation.
LOCATION: Both directions, SR 3, Shelton, milepost 0 to 25.
EXPECT: Mobile shoulder closure.
US 101, SR 101 South
Duke Stryker, 360-874-3050
TIME/DAYS: 8 a.m. to 3 p.m. Monday, April 8 to Tuesday, April 9.
DESCRIPTION: Sweeping operation.
LOCATION: Both directions, US 101, SR 101 South, mileposts 342 to 360.
EXPECT: Mobile shoulder closure.
US 101, Becon Point to Hamma Hamma
Duke Stryker, 360-874-3050
TIME/DAYS: 8:30 a.m. to 3:30 p.m. Tuesday, April 9 to Thursday, April 11.
DESCRIPTION: Vegetation management.
LOCATION: Both directions, US 101, Becon Point to Hamma Hamma, mileposts 315 to 319.
EXPECT: One-way, alternating traffic.
top
CONSTRUCTION
I-5/SR 16, Eastbound Nalley Valley Project
Neal Uhlmeyer, Project Engineer, 360-412-3420
www.wsdot.wa.gov/Projects/PierceCountyHOV/SR16_EBNalleyValley/
This project demolishes the existing eastbound viaduct at I-5/SR 16, constructs an improved eastbound viaduct structure, and opens a new ramp between South Sprague Avenue and eastbound SR 16.
TIME/DAYS: See below for specifics.
DESCRIPTION: ITS System work, erosion control measures, bridge demolition, installing bridge decking and girders, building retaining walls, and asphalt paving.
LOCATION: Northbound I-5 at SR 16, milepost 131 to 133, and both directions of SR 16, between I-5 and Union Street, mileposts 0.0 to 1.
EXPECT: Impact to city streets. South Tacoma Way and South Center Street will have lane closures in both directions from Wilkeson Street to Pine Street 6:00 a.m. to 6:00 p.m. daily. South Sprague Avenue will have a northbound detour Monday-Friday.
SR 161, 24th Street E. to Milton Way Widening
Jeff Cook, Project Engineer, 360-874-3010
www.wsdot.wa.gov/projects/sr161/36th_jovita/
This project improves safety and eases congestion by adding lanes and managing access. Improvements for the first phase includes adding one through-lane each direction from 24th Street to Milton Way (1.2 miles), as well as sidewalks, and 4-foot shoulders to accommodate bicycles. Additionally, driveways to the highway will be consolidated and defined. A new traffic signal will be built at the intersection with 16th Street.
TIME/DAYS: 6:30 a.m. to 4:30 p.m. Monday-Friday, through April 12.
DESCRIPTION: Installation of a joint utility trench, water line and erosion control work.
LOCATION: Both directions of SR 161 from 24th Street to Milton Way, mileposts 32 to 33.
EXPECT: Short term traffic stops for trucks entering and exiting the roadway. Some lanes may be temporarily restriped to accommodate the construction zone.
NIGHTTIME WORK: One-way alternating traffic for both directions of SR 161 from 24th Street to Milton Way, mileposts 32 to 33 from 7 p.m. to 5 a.m. Monday, April 8 to Thursday, April 11.
I-5, SR 510 to SR 512 ITS Fiber Improvements
MaryLou Nebergall, 253-365-6750
TIME/DAYS: 9 a.m. to 3 p.m. Monday-Friday, April 8-12.
DESCRIPTION: Contractor is starting preliminary setup for fiber optic improvements. Motorists may notice new signs, dirt work and fencing installation.
LOCATION: Northbound I-5, from Hawks Prairie to SR 512, milepost 112 to 128.
EXPECT: Right-lane shoulder closures.
MAINTENANCE
I-5, Yakima Avenue
Tony Kilmer, 360-357-2763
TIME/DAYS: 8:30 p.m. to 1 a.m. Monday April 8.
DESCRIPTION: Drilling.
LOCATION: Northbound I-5, Yakima Avenue to Pacific Avenue, mileposts 133 to 134.36.
EXPECT: Left lane closure.
SR 161, Eatonville
Chris Ehresmann, 360-570-6749
TIME/DAYS: 8 a.m. to 4:30 p.m. Monday-Friday, April 8-12.
DESCRIPTION: Utility work.
LOCATION: Both directions of SR 161, Eatonville Cutoff Road to 400th, milepost 6.
EXPECT: One-way, alternating traffic.
SR 161, Puyallup
Chris Ehresmann, 360-570-6749
TIME/DAYS: 10 p.m. to 5 a.m. Wednesday, April 10 to Thursday, April 11.
DESCRIPTION: Utility work.
LOCATION: Southbound, SR 161, 156th Street East 158th Street East, mileposts 22.32 to 22.56.
EXPECT: Right lane closure.
SR 167, Puyallup
Tom Gibbs, 253-983-7550
TIME/DAYS: 10:30 p.m. to 4:30 a.m. Tuesday, April 9 to Thursday, April 11.
DESCRIPTION: Roadside maintenance.
LOCATION: Both directions, SR 167, Puyallup, milepost 6 to 11.
EXPECT: Left lane closure.
SR 410, Sumner
Tom Gibbs, 253-983-7550
TIME/DAYS: 10:30 p.m. to 4:30 a.m. Sunday, April 7 to Tuesday, April 9.
DESCRIPTION: Roadside maintenance.
LOCATION: Both directions, SR 410, Sumner, milepost 8 to 13.
EXPECT: Left lane closure.
top
CONSTRUCTION
I-5, SR 510 to SR 512 ITS Fiber Improvements
MaryLou Nebergall, 253-365-6750
TIME/DAYS: 9 a.m. to 3 p.m. Monday-Friday, April 8-12.
DESCRIPTION: Contractor is starting preliminary setup for fiber optic improvements. Motorists may notice new signs, dirt work and fencing installation.
LOCATION: Northbound I-5, from Hawks Prairie to SR 512, milepost 112 to 128.
EXPECT: Right-lane shoulder closures.
MAINTENANCE
SR 8, Kennedy Creek Road
Randy Moody, 360-538-8530
TIME/DAYS: 7:30 a.m. to 11:30 a.m. Monday, April 8.
DESCRIPTION: Roadside maintenance.
LOCATION: Westbound SR 8, Kennedy Creek Road, mileposts 15.4 to 15.5.
EXPECT: Left lane closure.
top