SR 153 - Methow River Bridges - Deck and Rail Repair - Complete July 2008

Project Status - Complete
The orange line shows the project location on SR 153 in Okanogan County.
View entire map
  This project is located between Pateros and Carlton on SR 153 between milepost 3 and milepost 16 in Okanogan County.

Click to enlarge
View entire photo
  This is the new bicycle/pedestrian sidewalk on Bridge 14.

Click to enlarge
View entire photo 
There were temporary signals at two bridges for the 2nd season.
See more construction photos

An example of damaged bridge rail.
View entire photo. An example of damaged bridge rail.

This bridge rail is actually broken.
View entire photo. This bridge rail is actually broken.

An example of sidewalk damage.
View entire photo An example of sidewalk damage.

More photos

Overview
This Structure Preservation Project repaired five bridges over the Methow River in a 12-mile segment of SR 153.  The decks, rails and sidewalks showed marked signs of deterioration on Bridges 153/3, 153/4, 153/10, 153/14, and 153/15. Concrete deck surfaces were repaired - four were overlaid with Hot Mix Asphalt (3,10,14,15). Bridge rails were repaired on all five. Sidewalks on two (10,14) were retrofitted with supports.

Season one construction began in April, 2007 and was complete on September 13th. Season two construction began April 21, 2008 and was complete July 30th.

How You Benefit
Cross GlyphImproves Safety
Renovating the bridge deck, updating guardrail terminals, placing new thrie-beam guardrail along the sidewalks and retrofitting sidewalks with supports provides a safer corridor for both motorists and pedestrians.
Leaf Glyph Protects Environment
The following are the permits and/or documentation that were required for this project:

-NEPA (CE) - National Environmental Policy Act of 1969
-SEPA (CE) - State Environmental Policy Act of 1971.
-BA - Biological Assessment.
-Temporary Erosion Control Plan.
-HPA - Hydraulic Permit approval
-Shoreline

Partnerships & Cooperation
Besides the safety benefits of the project itself, safety for the public and the construction workers is paramount while the work is underway. A comprehensive traffic control plan and a work zone safety plan was implemented to protect travelers and workers.

Funding

The project was advertised for private contractor bids in November, 2006 and three qualified bids were opened on December 14th. A $2,341,718.35 contract was awarded to MRM Construction Inc. on December 21st.

This project is funded through the following sources:

  • Pre-Existing Gas Tax- $3.18 million
  • Total funding from all sources- $3.18 million

Contact Us
Project Engineer Eric Pierson
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone: (509) 667-2870 or toll free (888) 461-8816
Email: piersoe@wsdot.wa.gov