View entire map This project is located at milepost 70.21 under the westbound lanes of US 2 in western Chelan County.

View entire photo Strider crews work to rebuild the roadbed over the new pipe arch on September 13th.
View entire photo Mill Creek inlet at high volume.

View entire photo Closer View of Mill Creek outlet at high volume.
Project Facts
- Eastbound lanes of US 2 were used as a detour during construction.
- 985 cubic yards of streambed material was used to create the new streambed under the culvert.
- Construction began July 10th and was complete in October.
Project was complete October 5th, 2006
This Environmental Retrofit Improvement Project removed a Fish Barrier on Mill Creek under US 2 near Stevens Pass.
Why is WSDOT
Replace the existing culvert?
The undercrossing of Mill Creek was identified as deficient for fish passage by the Washington State Department of Wildlife. The original culvert was an 11-foot corrugated metal culvert.
The End Result
The 11-foot metal culvert was replaced with a 38-foot span bottomless plate arch that allows adequate fish passage in a more natural environment.
Project Benefits
- Improves fish migration.
- Increases culvert capacity to accommodate a 100-year storm water runoff.
What is the project timeline?
Construction began July 24th and was complete October 5th, 2006.
Public Involvement
Your thoughts and opinions are important to us. If you have any questions or concerns about this project please contact the Project Office, listed below.
Environmental Protection
All environmental laws and guidelines were strictly followed. The followings are the permits and/or documentation required for this project:
- Environmental Project Documentations:
- NEPA (CE) - National Environmental Policy Act of 1969.
- SEPA (CE) - State Environmental Policy Act of 1971.
- BA - Biological Assessment.
- Temporary Erosion Control Plan.
- SHPO Consultation.
Environmental Project Permits:
- HPA - Hydraulic Project Approval
- Army Corps of Engineer.
- Section 401 - Water Quality Certification.
Please visit the
WSDOT Environmental
Services Web site for more information.
Increasing safety is one of our priorities
Safety for the public and the construction workers is paramount while the work is underway. During construction, a comprehensive traffic control plan and a work zone safety plan was in effect to protect travelers and workers.
Will this project impact tribal resources?
No impacts to tribal resources were found, during a cultural resource survey conducted prior to construction. WSDOT seeks to address the concerns of tribal nations using the process outlined in Section 106 of The National Historic Preservation Act and the WSDOT Tribal Consultation Policy adopted in 2003 by the Transportation Commission as part of the WSDOT Centennial Accord Plan.
Financial Information
This project was advertised for private contractor bids on March 27th, 2006. Four bids were opened May 4th. Contract # 7143 was awarded to Strider Construction Co. Inc. for $1.177,634. on May 9th.
This project was funded through the following source:
- Pre-Existing Gas Tax - $1.69 million
- Total funding from all sources - $1.69 million
How can I get more information?
Contact:
Kevin Waligorski, Project Engineer
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone: (509) 667-2860 or toll free (888) 461-8816
E-mail: waligok@wsdot.wa.gov
back to top