US 2 - Cashmere East - Paving

Project was complete August 17, 2006
The project repaves US 2/97 between Cashmere and Wenatchee.  View entire map  This project is located on US 2/97 between MP 109.85 and MP 117.62.

Click to enlarge
View entire photo
  Mainline paving got underway in May.

patched distressed pavement
View entire photo
 An example of the damage the repaving will fix.


View entire photo
  Rutting is apparent at the Cotlets Way intersection. 


View entire photo
  Hay Canyon right turn lane will be extended, increasing storage capacity and reducing the potential for rear end collisions.

Status

This project was substantially complete August 17, 2006.

This roadway preservation project paves 7.77 miles of highway between Cashmere and Wenatchee in Chelan County.

Why is WSDOT paving US 2/97?
The current road surface is deteriorating, particularly at intersections that have become severely rutted.  Repaving now, preserves the existing pavement structure and extends pavement service life.  The project also many includes safety improvements.

The End Result
A safer highway and a smoother driving surface and extended roadway life.  This will be achieved by overlaying the existing pavement with 2 inches of Hot Mix Asphalt (HMA).  Driving lanes at three intersections will be ground down and filled and overlayed with a stronger,stiffer asphalt material to resist future rutting. 

Project Benefits

  • Preserve the pavement for the next 10 to 15 years.
  • Provides a smoother driving surface and reduces future rutting at intersections. 
  • Improves safety with new: 
    • Illumination at Cotlets Way, and Old Monitor Rd. 
    • Reflectorized recessed pavement markers and barrier delineators.
    • Shoulder rumble strips, striping and signage.
  • Hay Canyon Road right turn lane will be extended, increasing storage capacity and reducing the potential for rear end collisions on US 2/97.

What is the project timeline?
Construction began April 3rd, 2006 and was estimated to be complete in 13 weeks (65 working days).  The project was complete on August 17, 2006. 

Financial Information

The project was advertised for private contractor bids on November 7th, 2005.  Two bids were opened December 8th.  December 12th, contract # 7059 was awarded to Basin Paving Company for $2,587,144.17.

This project is funded through the following sources:

  • Pre-Existing Gas Tax - $3.25 million
  • Total funding from all sources - $3.25 million

How can I get more information?
Contact:
Kevin Waligorski, Project Engineer
WSDOT - North Central Region
PO Box 98
Wenatchee, WA 98807
Phone: 509-667-2860 or toll free 1-800-461-8816
Email: WaligoK@wsdot.wa.gov

back to top