Project Title & Location
SR 285 Wenatchee Area - Paving
|
Project Description
This project will grind and replace the existing asphalt concrete pavement to resurface this section of SR 285.
|
|
Contractor/Consultant
This project is in the Design Phase and has not yet been advertised or awarded.
|
|
Recent Progress
Began Coordination with the City of Wenatchee in February, 2004. Met with the Wenatchee City Council for a workshop session on April 15, 2004. Regular monthly communications with the City are ongoing. Open house with local businesses on June 10, 2004, with a general public open house planned for Fall, 2004.
|
|
Design Construction Impacts
Construction activities will require close coordination with the City of Wenatchee, local merchants, schools, and emergency services.
|
|
Environmental Impacts / Compliance
No environmental impacts. No permits anticipated.
NEPA: Categorically excluded
SEPA: Categorically exempt
|
Impacts to Traffic
Coordinating with City and the public to establish ways of mitigating impacts to the traveling public, businesses and pedestrians during construction.
|