SR 285 - Wenatchee Area - Paving

Quarterly Project Report Update for Quarter Ending March 2004

Project Title & Location
SR 285 Wenatchee Area - Paving

Project Description
This project will grind and replace the existing asphalt concrete pavement to resurface this section of SR 285.

Contractor/Consultant
This project is in the Design Phase and has not yet been advertised or awarded.

Recent Progress
Began Coordination with the City of Wenatchee in February, 2004.  Field review scheduled for March 17, 2004.  City Council meeting workshop planned for April 15, 2004. 

Design Construction Impacts
Construction activities will require close coordination with the City of Wenatchee, local merchants, schools, and emergency services.

Environmental Impacts / Compliance

No environmental impacts.  No permits anticipated. 

NEPA:  Categorically excluded                    

SEPA: Categorically exempt

Impacts to Traffic

Coordinating with City and the public to establish ways of mitigating impacts to the traveling public, businesses and pedestrians during construction.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised October 11, 2004 On Schedule
Contract Awarded November 18, 2004 On Schedule
Groundbreaking Spring 2005 To be determined through public involvement.
Open to Traffic Fall 2005

Project area is anticipated to be continually open to traffic through construction.

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.2 6.9%
Right-of-Way $0.0 0.0%
Construction $2.7 93.1%
Funded Project Costs $2.9 100%

Nickel funds included in above costs

$0.0 0%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Bob Romine, WSDOT Project Engineer @ (509) 667-2880 Or Email:  Romineb@wsdot.wa.gov