WSDOT Projects

text size: T T T

SR 28 - Crescent Bar to Quincy - Paving

Project was completed July 31st, 2007
Click to enlarge View entire map This project is located on SR 28 between MP 19.12 to MP 27.73 in western Grant County.

Click to enlarge
View entire photo
  New guardrail, like this on Trinidad Hill was included in the project. 

click to enlarge
View entire photo
  The Quincy Safety Rest Area was repaved and restriped as part of this project.


 View entire photo
  Additional pavement repair was done at the Burlington Northern Railroad undercrossing to add structural strength to the pavement.


View entire photo
 Wetland areas were not be disturbed during construction.
 
Project Facts
  • This project repaved 8.61 miles of SR 28.
  • Safety improvements include guardrail upgrades, restriping, centerline rumble strips, and installing new guide posts.
  • Sidewalk ramps at the Quincy Valley Safety Rest Area were upgraded to current ADA standards.

Project Status

This project was completed July 31st, 2007

 

This Roadway Preservation project repaved 8.61 miles of SR 28, west of Quincy.

Why is WSDOT pave SR 28?
SR 28 is deteriorating and repaving when we did, at the lowest life-cycle cost, preserves the load carrying capacity and upgrades the safety features of the roadway.

The End Result
This project restored the structural integrity of the pavement. It also improved safety by installing new, higher visibility striping, installing centerline rumble strips, and updating guardrail. The Quincy Valley Safety Rest Area parking lot was seal coated to preserve the surface. Sidewalk ramps in the rest area were fitted with "truncated dome" pads to assist sight impaired pedestrians and to comply with new American's with Disabilities Act standards.

Project Benefits

  • Extends roadway life.
  • Provides a smoother driving surface.
  • Installs centerline rumble strips.
  • Improves the Quincy Rest Area facilities.

What is the project timeline?
Construction began May 14th and was completed July 31st, 2007. (43 working days).

Public Involvement
Your thoughts and opinions are important to us. If you have any comments or questions please contact the project engineering office listed below.

Environmental Protection
All environmental laws and guidelines were followed. 
The following are the permits and/or documentation required for this project:

  • Environmental Project Documentation:
    • NEPA (DCE) - National Environmental Policy Act of 1969
    • SEPA (CE) - State Environmental Policy Act of 1971
    • Biological Assessment
    • TESC - Temporary Erosion and Sediment Control Plan

Please visit the WSDOT Environmental Services Web site for more information.

Increasing safety is one of our priorities
In addition to the safety benefits of the project itself, a traffic control plan to protect motorists during construction and a work zone safety plan for the crews on the site was in effect.

Will this project impact tribal resources?
No cultural or archeological impacts have been identified.  WSDOT seeks to address the concerns of tribal nations using the process outlined in section 106 of The National Historic Preservation Act and the WSDOT Tribal Consultation Policy adopted in 2003 by the Transportation Commission as part of the WSDOT Centennial Accord Plan. 

Financial Information
The project was advertised for private contractor bids On September 11th and bids were opened on October 12th.  On October 16th, Basin Paving Company was awarded contract #7204 for $1,425,936.25, 17% under the engineering estimate.

This project was funded from the following sources: 

  • Pre-Existing Funds - $2.5 million
  • Total funding from all sources - $2.5 million

How can I get more information?
Contact:
Kevin Waligorski, Project Engineer
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone: (509) 667-2860 or toll free (888) 461-8816
E-mail: waligok@wsdot.wa.gov

back to top