WSDOT Projects

text size: T T T

SR 17 - Franklin County Line to Othello - Paving - Complete June 2006

Project was complete June 12,2006
The orange line shows the 6 mile section of SR 17 that will be paved.
View entire map.  This SR 17 paving project, from Milepost 21.8 to 27.79, is located in Adams County.

Rumble Strips, like these further north on SR 17 will be installed as part of this project.

View entire photo  Rumble strips, like these on SR 17 between Othello and Moses Lake were extended to the Franklin County line as part of this project.

Project Facts
  • This project ground off approximately 2-inches of the existing road surface and replaced it with a new surface of Hot Mix Asphalt (HMA).
  • Construction began May 1st and was complete June 12th.
  • Both centerline and shoulder rumble strips were added throughout the project.

Project Status

Project was complete on June 12th, 2006

 

This Preservation Project paved 6 miles of SR 17 in Adams County south of Othello.

Why is WSDOT pave SR 17?
This section of SR 17, from the Franklin County Line to just south of the SR 17/SR 26 Interchange, at Othello, needed pavement restoration.  A layer of asphalt was ground off, damaged sections repaired, and then it was repaved with Hot Mix Asphalt.

The End Result
The project prevents further deterioration to the existing roadway at the least possible "life cycle" cost.

Project Benefits

  • Extends roadway life.
  • Provides a smoother driving surface.
  • Installs both centerline and shoulder rumble strips.

What is the project timeline?
Construction began May 1st, 2006 and was complete June 12th (within the contracted 30 working days).

Public Involvement
Your thoughts and ideas are important to us.  If you have questions or concerns about this project, please contact the project engineering office listed below.

Environmental Protection

WSDOT is committed to protecting the environment.  All environmental laws and guidelines will be strictly followed. 

The following are the procedures, documentation or permits required for this project:

    • NEPA (CE) - National Environmental Policy Act of 1969.
    • SEPA (CE) - State Environmental Policy Act of 1971.
    • BA - Biological Assessment, Federal Highway Administration/EPA 
    • TESC - Temporary Erosion Control Plan, FHWA/EPA

Please visit the WSDOT Environmental Services Web site for more information.

Increasing safety is one of our priorities
Besides the safety benefits of the project itself, safety for the public and the construction workers is paramount while the work is underway. A comprehensive traffic control plan and a work zone safety plan was implemented to protect travelers and workers.

Will this project impact tribal resources?
After a thorough review, no impacts were identified.  WSDOT addresses the concerns of tribal nations using the process outlined in Section 106 of the National Historic Preservation Act and the WSDOT Tribal Consultation Policy adopted in 2003 by the Transportation Commission as part of the WSDOT Centennial Accord Plan.

Financial Information

This project went out for bids on October 31st, 2005.  Three bids were opened on December 1st. December 5th, contract # 7060 was awarded to Central Washington Asphalt, Inc. for $778,719.10, 7% under the engineering estimate.

This project is funded through the following sources:

  • Pre-Existing Gas Tax - $1.1million
  • Total funding from all sources - $1.1 million

How can I get more information?
Contact:
Mike Fleming, Project Engineer
WSDOT North Central Region
P.O. Box 98
Wenatchee, WA 98807
Phone:  (509) 667-2870 or toll free (888) 461-8816
Email:  fleminm@wsdot.wa.gov

back to top