Traveler Advisory & Construction Update for May 17-27, 2018

=  =  =  =  =

Highway Construction and Maintenance scheduled projects

US 2-Division Street-Browne Street-Ruby Street/I-90 to Euclid Ave. (MP 286-289)
Highway: US 2 Region: Eastern County: Spokane Location: MP 286-289
Description: Asphalt grinding and re-paving. ADA sidewalk ramp improvements.
Website: www.wsdot.wa.gov/projects/us2/i90-euclid/home
Work Schedule: Drivers should be alert for daytime lane restrictions for ADA work. During evening and overnight hours, drivers should expect multiple lane closures for paving and/or asphalt grinding.
Contact: Chad Simonson, project engineer, 509-324-6252

= =

US 2-West of Farwell Road/Costco Access Roundabout- (MP 295)Highway: US 2 Region: Eastern County: Spokane Location: MP 295
Description: Construct a new 2 lane roundabout intersection between Winchester Road and Farwell Road for access to the new Costco development.
Work Schedule: US 2 is reduced to one lane in each direction. Drivers should be alert for slow traffic, congestion, and delays, especially during commute hours, and may wish to seek alternate routes. Also, motorists need to be alert for trucks entering and exiting the roadway.
Contact: This is a Costco Wholesale Corporation project, Contact Lydig Construction-Travis Semler at 509-534-0451

= =

US 2/Deer Road to Colbert Road – Paving and turn lane improvements (MP 297-300)
Highway: US 2 Region: Eastern County: Spokane Location: MP 297-300
Description: Asphalt paving and turn lane improvements.
Website: www.wsdot.wa.gov/Projects/US2/deerrdtodaymtspokane
Work Schedule: Drivers should be alert for possible lane restrictions during non-commute hours, Monday through Friday Contact: Mark Allen, project engineer, 509-324-6232

= =

SR 21/Cannawai Creek to US 2 (MP 74.00 – 91.78)
Highway: SR 21 Region: Eastern County: Adams Location: MP 74.00 - 91.78
Description: Crack seal, pavement repair, prelevel in prep for upcoming chip seal.
Work Schedule: Drivers should be alert for flaggers and or pilot cars directing single-lane, alternating traffic with some delays when work is underway.
Website: www.wsdot.wa.gov/Projects/chipseal/eastern-2018/home
Contact: Chad Simonson, project engineer, 509-324-6252

= = =

SR 21/Lind to I-90 (MP 24.77 – 37.71)
Highway: SR 21 Region: Eastern County: Adams Location: MP 24.77 – 37.71
Description: Bridge deck HMA removal and repair, crack seal, pavement repair, prelevel.
Work Schedule: Drivers should be alert for flaggers and or pilot cars directing single-lane, alternating traffic with some delays when work is underway.
Website: www.wsdot.wa.gov/Projects/chipseal/eastern-2018/home
Contact: Chad Simonson, project engineer, 509-324-6252

= =

SR 25/Vicinity of Two Rivers & Fort Spokane-Spokane River Bridge Embankment Repairs- (MP 23)
Highway: SR 25 Region: Eastern County: Stevens Location: MP 23
Description: Stabilize slopes adjacent to west end of bridge .
Work Schedule: Motorists should be alert for temporary traffic signal controlling single-lane, alternating traffic across bridge with delays of about 3 to 4 minutes, 24/7.
Website: www.wsdot.wa.gov/projects/sr25/spokane-river-bridge/home
Contact: Tom Brasch, project engineer, 509-323-8411

= =

SR 41/BNSF-POVRR Railroad Bridge (MP 38)
Highway: SR 41 Region: Eastern County: Pend Oreille Location: MP 38
Description: Replace the bridge over the railroad tracks just south of Newport, Washington, and Oldtown, Idaho. This bridge is jointly owned by the Idaho Transportation Department and WSDOT. This is an Idaho Transportation Department project.
Website: www.itd.idaho.gov/d1/
Work Schedule: The bridge is reduced to one lane with temporary signalization. The nearby intersection of Fourth Street will be closed with a detour on Marion Street posted.
Contact: Megan Sausser, Idaho Transportation Department Communications, (208) 772-1295

= =

US 195/Colton to Pullman (MP 10-19)
Highway: US 195 Region: Eastern County: Whitman Location: MP 10-19
Description: Asphalt pavement patching
Work Schedule: On Monday, Wednesday, and Thursday; May 21, 23, and 24, between 7 a.m. until as late as 5 p.m., drivers should expect flaggers and pilot cars directing single-lane, alternating traffic at work locations with delays up to 15 minutes.

= =

US 195/Bridge Deck Repairs-Vicinity of Steptoe and Rosalia (MP 48, 63, 65)
Highway: US 195 Region: Eastern County: Whitman Location: MP 48, 63, 65
Description: Grind out concrete pavement, repair base as needed and resurface with concrete.
Work Schedule: Motorists should be alert for temporary traffic signals near Rosalia and near Steptoe) with delays at each location, adding up to 10 extra minutes for the trip.
Website: https://wsdot.wa.gov/projects/us195/bridge-deck/home
Contact: Mark Allen, project engineer, 509-324-6232

= =

US 195/Colfax to Spangle-Passing Lanes Phase 2 (MP 56, 68, 70 & 72)
Highway: US 195 Region: Eastern County: Spokane & Whitman Location: MP 56, 68, 70 & 72
Description: Add 4 new passing lane segments.
Work Schedule: Drivers should be alert for possible, short-term, shoulder or lane restrictions.
Website: www.wsdot.wa.gov/Projects/US195/colfaxtospanglepassinglanes/
Contact: Mark Allen, project engineer, 509-324-6232

= =

SR 261/Sutton to I-90 (MP 44.85 – 62.67)
Highway: SR 261 Region: Eastern County: Adams Location: MP 44.85 – 62.67
Description: Crack seal, pavement repair, prelevel. Pavement repair and prelevel paving.
Work Schedule: Drivers should be alert for flaggers and or pilot cars directing single-lane, alternating traffic with some delays when work is underway.
Website: www.wsdot.wa.gov/Projects/chipseal/eastern-2018/home
Contact: Chad Simonson, project engineer, 509-324-6252

= = =

SR 291/ Charles Road to Suncrest (MP 9-14)
Highway: SR 291 Region: Eastern County: Spokane & Stevens Location: MP 9-14
Description: Grind out old asphalt and resurface
Work Schedule: Beginning on Tuesday, May 22 from 7 p.m. until 6 a.m. during the week, drivers should expect delays with flaggers and/or pilot cars directing single-lane, alternating traffic at work locations.
Website: https://www.wsdot.wa.gov/projects/sr291/charles-road-suncrest/home
Contact: Tom Brasch, project engineer, 509-323-8411

= =

SR 290-Trent Ave./Perry Street Roundabout- (MP 1)
Highway: SR 290 Region: Eastern County: Spokane Location: MP 1
Description: Construct single lane roundabout at the Trent Ave./Perry Street intersection to facilitate new Martin Luther King Way
Work Schedule: SR 290/Trent Ave. is fully closed just east of Hamilton at Perry Street. Signed detours available.
Website: https://my.spokanecity.org/projects/riverside-drive-phase-2b/
Contact: Marlene Feist, 509-625-6505. This is a City of Spokane project.

= =

NSC-US 395/Freya Structures (MP 162)
Highway: US 395 Region: Eastern County: Spokane Location: NSC MP 162
Description: Construct two mainline freeway bridges over Freya Street
Project Website: www.wsdot.wa.gov/Projects/US395/nspokanecorridorfreya/
Work Schedule: Drivers should be alert for occasional traffic control at the Freya roundabouts.
Contact: Mark Allen, project engineer, 509-324-6232