SR 433 - Lewis and Clark Bridge Deck Replacement - Complete August 2004

Quarterly Project Report Update for Quarter Ending March 2005

Project Title & Location
Lewis and Clark Bridge 433/1 Deck Replacement

Project Description
Replace the existing bridge deck of the Lewis and Clark Bridge, Number 433/1. Construction of the deck replacement stage of this project began in January, 2003. Half of the funding for this project is contributed by Oregon Department of Transportation. This project is constructed simultaneously with the navigational light system project, the seismic retrofit project, and the interim painting project.

Contractor/Consultant
Max J. Kuney - Spokane, Washington

Recent Progress
All contract work has been completed on the project.

Design Construction Impacts
All contract issues have been resolved with only processing of Change Orders left to complete.

Environmental Impacts / Compliance
Silt fences captured sediments from runoff to avoid impacts to the river, as outlined in the Temporary Erosion and Sediment Control Plan. The contractor implemented a containment plan to ensure lead from deck removal did not release into the environment. A Peregrine Falcon Management Plan helped avoid potential, adverse impacts from construction during the nesting activity.

Impacts to Traffic

124 weeknight full bridge closures, approximately 120 weeknight single-lane closures, and three full weekend bridge closures were required to complete the work. 

Project Milestones Scheduled Attained Milestone Outlook
Contract Awarded November 2002 December 2002 Delay due to six addendums.
Widen/Overlay Comp. October 2004 April 2004 Completed early.
Panel Install. Comp. October 2004 March 2004 Completed early.
Substantial Comp. October 2004  July 2004

Completed early.

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $.76 2.5%
Right-of-Way $.04 0.1%
Construction $29.83 97.4%
Funded Project Costs $30.63 100%

Nickel funds included in above costs

0 0

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Amy Revis, WSDOT Area Engineer, at (360) 442-1341or e-mail: lewisclarkbridge@wsdot.wa.gov