SR 433 - Lewis and Clark Bridge Deck Replacement - Complete August 2004

Quarterly Project Report Update for Quarter Ending June 2004

Project Title & Location
Lewis and Clark Bridge 433/1 Deck Replacement

Project Description
Replace the existing bridge deck of the Lewis and Clark Bridge, Number 433/1. Construction of the deck replacement stage of this project began in January, 2003. Half of the funding for this project is contributed by Oregon Department of Transportation. This project is constructed simultaneously with the navigational light system project, the seismic retrofit project, and the interim painting project.

Contractor/Consultant
Max J. Kuney - Spokane, Washington

Recent Progress
Deck replacement panels (103) are now installed on the bridge.  During the third and final full weekend bridge closure, rapid setting latex modified concrete was placed for a new roadway surface over 1500 feet on the Washington side and 80 feet on the Oregon side of the bridge.  Some other items now completed include new roadway lighting, seismic retrofit, new safety railing system for bridge inspections, and updated navigational lighting.

Design Construction Impacts
To date, an additional $5.3 million has been requested for additional work to the stringer-to-floorbeam connections that was not anticipated prior to construction.

Environmental Impacts / Compliance
Silt fences capture sediments from runoff to avoid impacts to the river, as outlined in the Temporary Erosion and Sediment Control Plan. The contractor implemented a containment plan to ensure lead from deck removal did not release into the environment. A Peregrine Falcon Management Plan is again helping to avoid potential, adverse impacts from construction during the nesting activity.

Impacts to Traffic

124 weeknight full bridge closures, approximately 120 weeknight single-lane closures, and three full weekend bridge closures were required to complete the work. 

Project Milestones Scheduled Attained Milestone Outlook
Contract Awarded November 2002 December 2002 Delay due to six addendums.
Widen/Overlay Comp. October 2004 April 2004 Completed early.
Panel Install. Comp. October 2004 March 2004 Completed early.
Substantial Comp. October 2004 June 2004

Completed early.

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $.76 3.0%
Right-of-Way $.04 0.2%
Construction $24.5 96.8%
Funded Project Costs $25.3 100%

Nickel funds included in above costs

0 0

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Amy Revis, WSDOT Area Engineer, at (360) 442-1341or e-mail: lewisclarkbridge@wsdot.wa.gov