Project Title & Location
Lewis and Clark Bridge 433/1 Deck Replacement
|
Project Description
Replace the existing bridge deck of the Lewis and Clark Bridge, Number 433/1. Construction of the deck replacement stage of this project began in January, 2003. Half of the funding for this project is contributed by Oregon Department of Transportation. This project is constructed simultaneously with the navigational light system project, the seismic retrofit project, and the interim painting project.
|
|
Environmental Impacts / Compliance
Silt fences captured sediments from runoff to avoid impacts to the river, as outlined in the Temporary Erosion and Sediment Control Plan. The contractor implemented a containment plan to ensure lead from deck removal did not release into the environment. A Peregrine Falcon Management Plan helped avoid potential, adverse impacts from construction during the nesting activity.
|
Impacts to Traffic
124 weeknight full bridge closures, approximately 120 weeknight single-lane closures, and three full weekend bridge closures were required to complete the work.
|