I-405 - Springbrook Creek Wetland & Habitat Mitigation Bank

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
Springbrook Wetland and Habitat Mitigation Bank (Nickel)

Project Description
This project is a partnership with the City of Renton to create a wetland bank. This wetland bank establishes compensatory mitigation in advance of unavoidable impacts to wetlands and other aquatic resources for future projects within the wetland bank’s service area (portions of WRIAs 8 and 9), including I-405. The wetland bank consists of five units, totaling 130 acres. As specified performance standards are met, incremental credits from the wetland bank become available for use.

Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.

Recent Progress
This project establishes compensatory mitigation in advance of unavoidable impacts to wetland and other aquatic resources for future projects within a portion of two watersheds: Water Resource Inventory Areas (WRIAs) 8 and 9, the Cedar-Sammamish Watershed and the Green-Duwamish Watershed.  The bank consists of five units, totaling 130 acres.  All relevant easements have been cleared, the Mitigation Bank Instrument was completed on time, and the project was advertised on schedule in August 2006.

Design Construction Impacts
There are no roadway construction impacts.  Impacts will be on property owned by the City of Renton and involve increasing the wetland area, improving the hydrologic, water quality, and habitat functions, increasing fish refuge/rearing habitat, and promoting environmental education.

Environmental Impacts / Compliance
A corridor wide Record of Decision for the programmatic FEIS was received in October 2002.  Project-level environmental documentation completed on January 10, 2006.

Impacts to Traffic
No roadway closures are expected, but public roadways will be used for removing earthwork materials from and delivering construction materials to the project site.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering Start (Nickel funding) July 2004 July 2004 Complete.
Finding of No Significant Impact/Complete Environmental Documentation Jan. 2007 Jan. 2006 Complete.
Right of Way Certification Oct. 2007 Certified as a RW Cert 3.  Project will be re-certified as a RW Cert 2 before bid opening.
Request For Proposal/Project Advertisement Jan. 2007 Project is on AD.  No issues at this time.
Open to Traffic/Wetland Completed June 2010 On schedule to complete wetland.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 2.1 13
Right-of-Way 0.2 1
Construction 14 86
Funded Project Costs 16.3 100

Nickel funds included in above costs

16.3 100

2005 Transportation Partnership Account

0 0

  For more information, go to www.wsdot.wa.gov/projects

Stacy Trussler, WSDOT Project Manager @ (425) 456-8563 or E-mail: trussler@wsdot.wa.gov