I-405 - Kirkland Nickel Stage 1 - Complete November 2007

Quarterly Project Report Update for Quarter Ending September 2004

Project Title & Location
I-405/SR 520 to SR 522 in Kirkland

Project Description
This project combines Kirkland Nickel Stage 2 and Transportation Partnership Account (TPA) components to add a continuous northbound and southbound lane between SR 520 and SR 522. Stage 2 adds one northbound lane from NE 70th Street to NE 85th Street, and one southbound lane from SR 522 to NE 124th Street and from NE 85th Street to the SR 520 area. TPA projects add a northbound lane from NE 124th Street to SR 522 and from NE 195th Street to SR 527.

Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.

Recent Progress
Engineering for this Nickel project is 50% complete toward the Design/Build package for the Request For Proposal (RFP).  Development of Request for Contractor Qualifications (RFQ) submittals 80% complete.  Right-of-way needs have been assessed.  Purchases expected from willing sellers over next 4 months. 

Design Construction Impacts

This is a widening project that will be constructed in two stages.  Stage 1 provides one additional lane in both the northbound and southbound directions from NE 85th to NE 124th.  Stage 2 provides one additional northbound lane from NE 70th to NE 85th and one additional southbound lane from SR 522 to NE 124th and from NE 85th to SR 520.

Environmental Impacts / Compliance
Completed 17 of 21 discipline reports for internal review.  Continue Multi-Agency Permitting Team (MAPT) coordination and review for project permits.  Expect to submit JARPA  and all other permit applications to MAPT Oct. 6, 2004.  Submitted corridor wide Land Use Analysis to FHWA and the Services August 2004.

Impacts to Traffic

Widening work is to the outside of the existing roadways so it is expected that Impacts to the traveling public can be minimized during construction. Close coordination continues with the adjacent Sound Transit direct access project: I 405 Totem Lake Freeway Station/ NE 128th.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering Start (Nickel funding) July 1, 2003 July 1, 2003 Nickel funding began on schedule.
Finding of No Significant Impact January 2006 Ahead of schedule by approximately 7 months with current target date of May 2005.
Right of Way Certification              Stage 1; Stage 2   October 2006;  October 2009 Stage 1 ahead of schedule by approximately 16 months with current target date of May 2005.
Request For Proposal            Stage1; Stage 2 April 2006;        April 2009

Stage 1 ahead of schedule by approximately 10 months with current target date of May 2005.

Open to Traffic  Stage1;  Stage 2 December 2008; December 2011 Stage 1 ahead of schedule by approximately 1 year with current target date of November 2007.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 21 13%
Right-of-Way 55 33%
Construction 88 54%
Funded Project Costs 164 100%

Nickel funds included in above costs

164 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Denise Cieri, WSDOT Segment Manager @ (425) 456-8509 or E-mail: cierid@wsdot.wa.gov