Project Title & Location
I-405/SR 520 to SR 522 in Kirkland
|
Project Description
This project combines Kirkland Nickel Stage 2 and Transportation Partnership Account (TPA) components to add a continuous northbound and southbound lane between SR 520 and SR 522. Stage 2 adds one northbound lane from NE 70th Street to NE 85th Street, and one southbound lane from SR 522 to NE 124th Street and from NE 85th Street to the SR 520 area. TPA projects add a northbound lane from NE 124th Street to SR 522 and from NE 195th Street to SR 527.
|
|
Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.
|
|
Recent Progress
Nickel funding began July 1, 2003. On October 2, 2003 the I-405 Executive Committee endorsed the Implementation Plan to guide future engineering design and environmental documentation. Have completed the 5 percent design which allows the Nickel project environmental documentation to begin. Held Nickel Public and Agency Environmental Document scoping meeting January 2004.
|
|
Design Construction Impacts
This is a widening project that will be constructed in two stages. Stage 1 provides one additional lane in both the northbound and southbound directions from NE 85th to NE 124th. Stage 2 provides one additional northbound lane from NE 70th to NE 85th and one additional southbound lane from SR 522 to NE 124th and from NE 85th to SR 520. The 2004 Legislative session approved the construction of this work in two stages with Stage 1 being the first I-405 project to begin construction.
|
|
Environmental Impacts / Compliance
A corridor wide Record of Decision for the programmatic FEIS was received in October 2002. Environmental documentation began January 2004 for the Kirkland Nickel work.
|
Impacts to Traffic
Widening work is to the outside of the existing roadways so it is expected that Impacts to the traveling public can be minimized during construction.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Preliminary Engineering Start (Nickel funding)
|
July 1, 2003
|
July 1, 2003
|
Nickel funding began on schedule.
|
|
Finding of No Significant Impact
|
January 2006
|
|
On schedule, no issues at this time.
|
|
Right of Way Certification Stage 1; Stage 2
|
October2006; October 2009
|
|
On schedule, no issues at this time.
|
|
Request For Proposal Stage 1; Stage 2
|
April 2006; April 2009
|
|
On schedule, no issues at this time.
|
|
Open to Traffic Stage1; Stage 2
|
December 2008; December 2011
|
|
On schedule, no issues at this time.
|