I-405 - Kirkland Nickel Stage 1 - Complete November 2007

Quarterly Project Report Update for Quarter Ending June 2005

Project Title & Location
I-405/SR 520 to SR 522 in Kirkland

Project Description
This project combines Kirkland Nickel Stage 2 and Transportation Partnership Account (TPA) components to add a continuous northbound and southbound lane between SR 520 and SR 522. Stage 2 adds one northbound lane from NE 70th Street to NE 85th Street, and one southbound lane from SR 522 to NE 124th Street and from NE 85th Street to the SR 520 area. TPA projects add a northbound lane from NE 124th Street to SR 522 and from NE 195th Street to SR 527.

Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.

Recent Progress

Engineering for the Nickel Stage 1 project is 95% complete and is currently in internal review.  Three contractors were short listed for bidding on the Proposal.  The Final Request for Proposal (RFP) is scheduled to be completed Mid to late July 2005.  The Contractors have the Draft Final RFP and are currently having one-on-one meetings with the I-405 Team.  Three right-of-way parcels for wetland mitigation have been acquired.  Two temporary construction easements have been acquired.

Design Construction Impacts

This is a widening project that will be constructed in two stages.  Stage 1 provides one additional lane in both the northbound and southbound directions from NE 85th to NE 124th.  Stage 2 provides one additional northbound lane from NE 70th to NE 85th and one additional southbound lane from SR 522 to NE 124th and from NE 85th to SR 520.

Environmental Impacts / Compliance
The Services concurred with the Biological Assessment at the end of October 2004.  The Environmental Assessment was signed February 23, 2005 with the Public comment period  ending on March 23, 2005.  The Finding of No Significant Impacts was obtained April 14th ahead of schedule with the final permits expected early July 2005.

Impacts to Traffic

Pavement is widened to the outside of the existing roadways so it is expected that impacts to the traveling public can be minimized during construction. Close coordination continues with the adjacent Sound Transit direct access project: I 405 Totem Lake Freeway Station/ NE 128th.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering Start (Nickel funding) July 1, 2003 July 1, 2003 Nickel funding began on schedule.
Finding of No Significant Impact January 2006 April 2005 Completed ahead of schedule.
Right of Way Certification              Stage 1; Stage 2   October 2005;     October  2009   Stage 1 is ahead of schedule by approximately 12 months.  Proposing Stage 2 advancement to October 2007 per 2005 Legislative Transportation Package.
Request For Proposal            Stage1; Stage 2 July 2005;     April 2009  

Anticipating awarding Stage 1 by November 2005.  Proposing Stage 2 advancement to July 2007 per 2005 Legislative Transportation Package.

Open to Traffic  Stage1;  Stage 2 December 2007; December 2011 Stage 1 is ahead of schedule by approximately 1 year with current target date of December 2007.  Proposing Stage 2 advancement to December 2010 per 2005 Legislative Transportation Package.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 21 13%
Right-of-Way 55 33%
Construction 88 54%
Funded Project Costs 164 100%

Nickel funds included in above costs

164 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Denise Cieri, WSDOT Segment Manager @ (425) 456-8509 or E-mail: cierid@wsdot.wa.gov