Project Title & Location
I-405/SR 520 to SR 522 in Kirkland
|
Project Description
This project combines Kirkland Nickel Stage 2 and Transportation Partnership Account (TPA) components to add a continuous northbound and southbound lane between SR 520 and SR 522. Stage 2 adds one northbound lane from NE 70th Street to NE 85th Street, and one southbound lane from SR 522 to NE 124th Street and from NE 85th Street to the SR 520 area. TPA projects add a northbound lane from NE 124th Street to SR 522 and from NE 195th Street to SR 527.
|
|
Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.
|
|
Recent Progress
Engineering for this Nickel project is 35% complete toward the Design/Build package for the Request For Proposal. Right-of-way needs have been assessed. Environmental Documentation scoping held Jan. 2004. Three of the 21 environmental discipline reports have been completed for internal review. Remaining reports expected by July. Held first MAPT (Multi-Agency Permit Team) meeting in May to begin permitting process.
|
|
Design Construction Impacts
This is a widening project that will be constructed in two stages. Stage 1 provides one additional lane in both the northbound and southbound directions from NE 85th to NE 124th. Stage 2 provides one additional northbound lane from NE 70th to NE 85th and one additional southbound lane from SR 522 to NE 124th and from NE 85th to SR 520.
|
|
Environmental Impacts / Compliance
A corridor wide Record of Decision for programmatic FEIS received in Oct 2002. Environmental documentation began Jan 2004. Completed 3 of 21 discipline reports for internal review. Began MAPT team coordination and review.
|
Impacts to Traffic
Widening work is to the outside of the existing roadways so it is expected that Impacts to the traveling public can be minimized during construction.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Preliminary Engineering Start (Nickel funding)
|
July 1, 2003
|
July 1, 2003
|
Nickel funding began on schedule.
|
|
Finding of No Significant Impact
|
January 2006
|
|
On schedule, no issues at this time.
|
|
Right of Way Certification Stage 1; Stage 2
|
October2006; October 2009
|
|
On schedule, no issues at this time.
|
|
Request For Proposal Stage 1; Stage 2
|
April 2006; April 2009
|
|
On schedule, no issues at this time.
|
|
Open to Traffic Stage1; Stage 2
|
December 2008; December 2011
|
|
On schedule, no issues at this time.
|