Project Title & Location
I-405/SR 520 to SR 522 in Kirkland
|
Project Description
This project combines Kirkland Nickel Stage 2 and Transportation Partnership Account (TPA) components to add a continuous northbound and southbound lane between SR 520 and SR 522. Stage 2 adds one northbound lane from NE 70th Street to NE 85th Street, and one southbound lane from SR 522 to NE 124th Street and from NE 85th Street to the SR 520 area. TPA projects add a northbound lane from NE 124th Street to SR 522 and from NE 195th Street to SR 527.
|
|
Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.
|
|
Recent Progress
Engineering for the Nickel project is 95% complete and is currently in internal review. Request for Contractor Qualifications went out Oct. 15th 2004 with Contractor Statement of Qualification due December 15th. The Draft Request for Proposal (RFP) is scheduled to be completed in early 2005. We expect to give the Draft RFP to the contractor at this time for information only. Right-of-way needs have been assessed and the first two parcels purchased November 2004. The remaining parcel should be purchased by early 2005.
|
|
Design Construction Impacts
This is a widening project that will be constructed in two stages. Stage 1 provides one additional lane in both the northbound and southbound directions from NE 85th to NE 124th. Stage 2 provides one additional northbound lane from NE 70th to NE 85th and one additional southbound lane from SR 522 to NE 124th and from NE 85th to SR 520.
|
|
Environmental Impacts / Compliance
Completed all 21 discipline reports for internal review. Multi-Agency permitting Team (MAPT) coordination continues to go well. All permit applications were submitted November 17th 2004. The Services concurred with the Biological Assessment at the end of October 2004. The Environmental Assessment is expected to be issued for public comments in early 2005 with a mid 2005 Finding of No Significant Impacts date.
|
Impacts to Traffic
Pavement is widened to the outside of the existing roadways so it is expected that Impacts to the traveling public can be minimized during construction. Close coordination continues with the adjacent Sound Transit direct access project: I 405 Totem Lake Freeway Station/ NE 128th.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Preliminary Engineering Start (Nickel funding)
|
July 1, 2003
|
July 1, 2003
|
Nickel funding began on schedule.
|
|
Finding of No Significant Impact
|
January 2006
|
|
Ahead of schedule by approximately 7 months with current target date of May 2005.
|
|
Right of Way Certification Stage 1; Stage 2
|
October 2006; October 2009
|
|
Stage 1 ahead of schedule by approximately 16 months with current target date of May 2005.
|
|
Request For Proposal Stage1; Stage 2
|
April 2006; April 2009
|
|
Stage 1 ahead of schedule by approximately 10 months with current target date of May 2005.
|
|
Open to Traffic Stage1; Stage 2
|
December 2008; December 2011
|
|
Stage 1 ahead of schedule by approximately 1 year with current target date of November 2007.
|