Recent Progress
Nickel funding began July 1, 2003. On October 2, 2003 the I-405 Executive Committee endorsed the Implementation Plan to guide future engineering design and environmental assessment.
Design team work has started on the Renton footprint design. A corridor-wide programmatic Endangered Species Act Biological Assessment is in progress as is a corridor-wide traffic forecast analysis.
Coordination is occurring with both Renton and Tukwila to reach agreement on I-405 improvement features.
|