Project Title & Location
I-405/SE 8th to I-90 (South Bellevue)
|
Project Description
This project combines the Bellevue Nickel project which builds one additional southbound lane from vicinity of NE 8th to I-90 and one additional northbound lane from I-90 to SE 8th with the TPA project to create a new northbound auxiliary lane from 112th Ave SE to I-90.
|
|
Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.
|
|
Recent Progress
Conducted Agency and Public Scoping Meetings for the Bellevue Nickel Project. Kicked off the Environmental Assessment process for the Bellevue Nickel Project. Held a utilities kickoff meeting with all of the utilities within the project limits. Completed Technical Reviews of the Bellevue Implementation Plan and Master Plan projects. Completed an Interdisciplinary Review of the Bellevue Nickel Project. Conducted CEVP workshop for the Bellevue Nickel Project and additional potential New Law projects. Worked with the City of Bellevue on the development of the NE 10th Extension Project. Made numerous presentations to: Bellevue Transportation Commission, Bellevue Arts Commission, Bellevue City Council, Bellevue Advisory Committee, as well as other Project Neighbors including condominium and neighborhood associations.
|
|
Design Construction Impacts
Expect moderate construction impacts. Plan to rebuild Wilburton tunnel within the center median area between Northbound and Southbound I-405 minimizing those potential construction impacts.
|
|
Environmental Impacts / Compliance
A corridor wide Record of Decision for the programmatic FEIS was received in October 2002. Project level environmental documentation began January 2005 with an agency and public scoping meeting. Submitted corridor wide Land Use Analysis to FHWA and the Services Aug 2004.
|
Impacts to Traffic
Will be more fully determined as this project's design is further along.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Preliminary Engineering Start (Nickel funding)
|
July 1, 2003
|
July 1, 2003
|
Nickel funding began on schedule.
|
|
Finding of No Significant Impact
|
July 2007
|
|
On schedule, no issues at this time.
|
|
Right of Way Certification
|
April 2008
|
|
On schedule, no issues at this time.
|
|
Request For Proposal
|
October 2007
|
|
On schedule, no issues at this time.
|
|
Open to Traffic
|
June 2011
|
|
On schedule, no issues at this time.
|