Project Title & Location
I-405/SE 8th to I-90 (South Bellevue)
|
Project Description
This project combines the Bellevue Nickel project which builds one additional southbound lane from vicinity of NE 8th to I-90 and one additional northbound lane from I-90 to SE 8th with the TPA project to create a new northbound auxiliary lane from 112th Ave SE to I-90.
|
|
Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.
|
|
Recent Progress
Nickel funding began July 1, 2003. On October 2, 2003 the I-405 Executive Committee endorsed the Implementation Plan to guide future engineering design and environmental documentation. Design team work has started on basemaps and surveying work. The right-of-way plan is in progress. A corridor-wide programmatic Endangered Species Act Biological Assessment is in progress as is a corridor-wide traffic forecast analysis.
|
|
Design Construction Impacts
Expect moderate construction impacts. Plan to rebuild Wilburton tunnel within the center median area between Northbound and Southbound I-405 minimizing those potential construction impacts.
|
|
Environmental Impacts / Compliance
A corridor wide Record of Decision for the programmatic FEIS was received in October 2002. Project level environmental documentation is expected to begin January 2005.
|
Impacts to Traffic
Will be more fully determined as this project's design is further along.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Preliminary Engineering Start (Nickel funding)
|
July 1, 2003
|
July 1, 2003
|
Nickel funding began on schedule.
|
|
Finding of No Significant Impact
|
July 2007
|
|
On schedule, no issues at this time.
|
|
Right of Way Certification
|
April 2008
|
|
On schedule, no issues at this time.
|
|
Request For Proposal
|
October 2007
|
|
On schedule, no issues at this time.
|
|
Open to Traffic
|
June 2011
|
|
On schedule, no issues at this time.
|