Project Title & Location
I-405/SE 8th to I-90 (South Bellevue)
|
Project Description
This project combines the Bellevue Nickel project which builds one additional southbound lane from vicinity of NE 8th to I-90 and one additional northbound lane from I-90 to SE 8th with the TPA project to create a new northbound auxiliary lane from 112th Ave SE to I-90.
|
|
Contractor/Consultant
HNTB Corporation is the lead consultant of the General Engineering Consultant Team.
|
|
Recent Progress
Continued developement of preliminary design project. Working closely with City of Bellevue to coordinate possible future crossing or interchange in the vicinity of NE 10th St. in Bellevue. Began Context Sensitive Solutions public process for design and aesthetics for the project. Began coordination with BNRR for future Wilburton Tunnel replacements options.
|
|
Design Construction Impacts
Expect moderate construction impacts. Plan to rebuild Wilburton tunnel within the center median area between Northbound and Southbound I-405 minimizing those potential construction impacts.
|
|
Environmental Impacts / Compliance
A corridor wide Record of Decision for the programmatic FEIS was received in October 2002. Project level environmental documentation is expected to begin January 2005 with an agency and public scoping meeting. Submitted corridor wide Land Use Analysis to FHWA and the Services Aug 2004.
|
Impacts to Traffic
Will be more fully determined as this project's design is further along.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Preliminary Engineering Start (Nickel funding)
|
July 1, 2003
|
July 1, 2003
|
Nickel funding began on schedule.
|
|
Finding of No Significant Impact
|
July 2007
|
|
On schedule, no issues at this time.
|
|
Right of Way Certification
|
April 2008
|
|
On schedule, no issues at this time.
|
|
Request For Proposal
|
October 2007
|
|
On schedule, no issues at this time.
|
|
Open to Traffic
|
June 2011
|
|
On schedule, no issues at this time.
|