I-205 - Mill Plain Exit - 112th Connector

Quarterly Project Report Update for Quarter Ending September 2004

Project Title & Location
I-205 Mill Plain/112th Avenue Connector

Project Description
This project will provide a direct connection to NE 112th Avenue from the off ramp of northbound I-205 to westbound Mill Plain Boulevard. It is a partnership project with the City of Vancouver.

Contractor/Consultant
Skillings-Connolly Inc.   

Recent Progress

The City of Vancouver hired Skillings-Connolly Inc. as the design engineers.  The city is responsible for the design phase of the project and WSDOT will provide general oversight during this phase.  WSDOT will administer the construction phase of the project.  Skillings-Connolly is continuing with design work and public outreach will begin this Fall.

Design Construction Impacts
At this time there are no known design issues that will impact the scope, schedule or budget for this project.

Environmental Impacts / Compliance
Impacts are unknown at this time.

Impacts to Traffic
None at this time.

Project Milestones Scheduled Attained Milestone Outlook
Design Start September 2003 December 2003 Design phase has started.
Record of Decision April 2005 No issues at this time.
Right of Way Complete March 2006 No issues at this time.
Ad Date April 2006 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering    
Right-of-Way    
Construction $12.0 100%
Funded Project Costs $12.0 100%

Nickel funds included in above costs

$12.0 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Don Owings, WSDOT Area Engineer, (360) 905-1500 or e-mail: i5MillPlain@wsdot.wa.gov