Project Title & Location
I-205 Mill Plain/112th Avenue Connector
|
Project Description
This project will provide a direct connection to NE 112th Avenue from the off ramp of northbound I-205 to westbound Mill Plain Boulevard. It is a partnership project with the City of Vancouver.
|
|
Contractor/Consultant
Skillings-Connolly Inc.
|
|
Recent Progress
The city of Vancouver, responsible for the design phase of the project, has hired Skillings-Connolly Inc. as the design engineers. Designers are working with I-205, Mill Plain to NE 28th St design team (Partnership project that has exit ramp from NB I-205 located immediately North of 112th Connector and braids with the NB I-205 onramp from Mill Plain) to redesign the Northbound I-205 onramp from Mill Plain with a second bridge. The noise study and environmental documentation is scheduled to be completed by the Mill Plain to 28th project team. The redesign provides a one-time construction impact to the NB onramp from Mill Plain.
|
|
Design Construction Impacts
The redesign of the NB onramp from Mill Plain and final design of the project are included in a new scope of work. Construction is being delayed with a current start date of Spring 2008.
|
|
Environmental Impacts / Compliance
Noise study to be completed
|
Impacts to Traffic
There will be impacts during construction including detour routes.
|