I-205 - Mill Plain Exit - 112th Connector

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location
I-205 Mill Plain/112th Avenue Connector

Project Description
This project will provide a direct connection to NE 112th Avenue from the off ramp of northbound I-205 to westbound Mill Plain Boulevard. It is a partnership project with the City of Vancouver.

Contractor/Consultant
Skillings-Connolly Inc.   

Recent Progress
WSDOT and the City of Vancouver are continuing to work together to advance the design of this project in close coordination with the I-205/Mill Plain to NE 18th St project. The project design is at ninety percent plans, specifications and estimate and progressing towards its construction date in 2008.

Design Construction Impacts
Construction is currently scheduled for Spring/Summer 2008 through 2009.  The Mill Plain northbound on-ramp and Mill Plain westbound off-ramp traffic will be detoured through the project area on temporary roadways. Anticipate several single lane weekend and intermittent single lane weekday closures on Interstate Route 205.

Environmental Impacts / Compliance
Environmental documentation, for this project and the I-205/Mill Plain to NE 18th St. Project, was completed in July 2007.

Impacts to Traffic
There will be impacts during construction, including ramp detour routes. Construction staging plans are developed. Anticipate minimal impacts to Interstate route 205 and moderate impacts to Mill Plain Blvd and 112th Ave.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering September 2003 December 2003 Design phase has started.
Record of Decision April 2005 July 2007
Right of Way Complete March 2006 Proceeding with access only acquisitions, complete March 2008.
Ad Date April 2006 Currently scheduled for Spring 2008.
Operationally Complete December 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering    
Right-of-Way    
Construction $12.7 100%
Funded Project Costs $12.7 100%

Nickel funds included in above costs

$12.7 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects