Project Title & Location
I-205 Mill Plain Interchange to NE 18th Street
|
Project Description
This project will improve safety and mobility in the area by constructing a new I-205 northbound off-ramp and southbound on-ramp at NE 18th Street and providing grade separated ramp connections.
|
|
Contractor/Consultant
David Evans and Associates Inc.
|
|
Recent Progress
WSDOT is currently in the preliminary design stage for this project. This effort requires close coordination with the I-205 Mill Plain Exit-112th Connector project, which is included in this project's environmental analysis. The preliminary project design has been completed enough to complete the environmental documentation.
|
|
Design Construction Impacts
Construction is currently scheduled for Spring/Summer of 2014 through 2016. Impacts are anticipated at Mill Plain, 9th Street, 18th Street and I-205.
|
|
Environmental Impacts / Compliance
Environmental documentation, for this project and the I-205 Mill Plain Exit-112th Connector, was completed in July 2007.
|
Impacts to Traffic
The design team will generate effective staging plans to minimize construction impacts to the traveling public.
|