Sept. 12 project update: Bertha back on the move

Posted on Sep 12 2016 3:33 PM
Seattle Tunnel Partners resumed mining today following a temporary stop to change tools on the cutterhead of Bertha, the SR 99 tunneling machine. As of lunchtime, crews were tunneling north approximately 170 feet below First Avenue, just north of Union Street.
 
Crews replaced a total of 14 large cutting tools during the two-week maintenance period. Bertha has moved from clay to a mixture of sand and gravel that wears down cutting tools more quickly. A photo comparing a new cutting tool with a worn cutting tool is available in this post.
 
The tools STP changed during this maintenance stop are the first parts of the cutterhead that contact the ground, making them crucial to the machine’s ability to excavate soil. STP will continue to inspect and replace these tools as needed during the course of mining. They are also planning Bertha’s next hyperbaric maintenance stop, the location of which is still being determined.
 
The machine has tunneled more than 4,135 feet and is nearing the halfway point of its 9,270-foot-long journey. The entire tunnel route, including descriptions of each of the 10 zones through which Bertha is mining, can be found on our Follow Bertha page. Tunneling statistics are updated on that page on Mondays and Thursdays. You can also track Bertha’s progress on Twitter @BerthaDigsSR99.
 
Recent tunneling updates 

 

Order: 1.2