North End

North End

 

A significant amount of construction continues at the SR 99 tunnel’s future north portal. The 80-foot-deep pit is where Bertha, the SR 99 tunneling machine, will emerge at the end of her two-mile journey beneath downtown Seattle.

Crews are also building the connection between the tunnel and Aurora Avenue North, and new on- and off-ramps at Republican Street. Our interactive simulation shows you how this area will change during construction.

When construction is complete, drivers, pedestrians and bicyclists will be able to travel between South Lake Union and Seattle Center via three improved east-west streets across the new Aurora Avenue North.      

Reminder: Long-term traffic impacts on SR 99 begin Monday, March 9

In one week, beginning Monday, March 9, crews building the future north portal of the SR 99 tunnel will close a single lane in both directions of SR 99/Aurora Avenue North between Valley Street and the Aurora Bridge. Two lanes will be open in each direction while crews install foundations for four large sign structures in the median and curb areas.

Closure details and schedule

Work is planned in two phases, starting with overnight lane closures on Monday, March 9 to set up the work zone. View a map of the work locations. 

  • Monday night, March 9
    • Beginning at 8 p.m., up to two lanes will be closed in both directions between Valley Street and the Aurora Bridge
    • Beginning at 10 p.m., SR 99/Aurora Avenue North will fully closed in the northbound direction between the south end of the Battery Street Tunnel and Valley Street
  • Phase 1 (approximately 8 weeks): one lane closed in both directions for median work
    • One lane in the northbound and southbound directions will be closed around-the-clock while crews install four sign foundations in the median
  • Phase 2 (approximately 4 weeks): one lane closed in southbound direction for curb work
    • One southbound lane will be closed around-the-clock while crews install two sign foundations in the southbound curb area

Durations shown for each phase are approximate and may change due to weather or other factors. We will keep the public informed as we prepare for Phase 2 work.

Bus rider information

Because northbound and southbound buses will travel, and stop, in the outside lanes with other vehicle traffic, trips into and out of Downtown Seattle may take longer than normal. During both phases the southbound bus-only lane restriction will be lifted.

Night work and weekend lane closures

In an effort to balance the needs of drivers and residents, an additional lane may close in both directions at night and during some weekend days. Some of this work is unavoidably noisy and may be disruptive. Residents with concerns related to nighttime noise may call 206-305-6967.

Driver tips

The long-term lane closures are expected to cause additional backups on SR 99 for vehicles and buses, particularly during peak commute times. WSDOT is encouraging drivers and bus riders to: 

  • Allow plenty of extra time and expect additional congestion, especially during peak commute times, on SR 99 between the Aurora Bridge and downtown.
  • If possible, consider leaving early, delaying your trip or telecommuting to avoid traveling during peak commute times in the morning and afternoon.
  • If you must drive, know before you go and use WSDOT's travel tools or visit SDOT’s travelers information page.
  • Share a ride in a car- or vanpool, or walk or ride a bicycle.

Questions?

Contact us at viaduct@wsdot.wa.gov or 1-888-AWV-LINE (298-5463) or visit us at www.AlaskanWayViaduct.org

Current construction near Dexter Avenue North

To make room for SR 99 tunnel construction, crews are relocating utilities along Dexter Avenue North and Republican Street.  

During this work, Dexter Avenue North will be reduced to one lane in each direction between Harrison and Mercer streets. A separate bicycle lane will be maintained on Dexter Avenue North during peak commute times. Depending on the work activity, signs may direct bicyclists to merge with traffic during off-peak hours. 

 

View a map (pdf 502KB) of the work zone. Our traffic Web page also includes up-to-date closure information.   

Other construction in the area

As you've likely noticed, the north end is bustling with construction activity. In addition to tunnel construction, our partners at the City of Seattle are making great progress on the Mercer Corridor Project. We’re coordinating closely with their construction, and will continue to do so as we move forward.