SR 99 - Alaskan Way Viaduct Replacement

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location

SR 99 - Alaskan Way Viaduct and Seawall Replacement Project

Project Description
The existing seismically vulnerable Alaskan Way Viaduct and Seawall are both at the end of their useful life and at risk of sudden and catastrophic failure in an earthquake. The cost to replace in-kind this seismically vulnerable structure is between $2.0 and $2.4 billion. (This figure does not include the cost of replacing the seawall or work north of Battery Street tunnel. Necessary to protect public safety and maintain the transportation corridor.

Contractor/Consultant
PB Americas is the prime design consultant. Hatch Mott MacDonald is the Program Management Assistant Consultant

Recent Progress
The “Moving Forward” projects as outlined by the Governor were the main focus for the team this quarter.   The team also completed 60% design of electrical relocation and mapping along Western Avenue to support the first utility relocation contract.  Work continues on the Construction Traffic Management Plan.  The Integrus property was purchased in June.

Design Construction Impacts
Design is approaching 60% complete for the Electrical Relocations - Phase 1 Project.  Design to the 30% level is otherwise commencing across the Program, with the exception of the Battery Street Tunnel Fire Life Safety Improvements Project, for which scope is being defined.  Roadway construction is planned to begin Winter 2009.

Environmental Impacts / Compliance
New SHPO procedures were developed for the “Moving Forward” projects.  The FHWA agreed to a revised Program Environmental strategy in June that supports the Moving Forward Projects.  Program Environmental staff is now developing the resulting environmental assessment documents.

Impacts to Traffic
Utilities construction, currently scheduled to begin Summer 2008, will impact traffic on local city streets.  Lane closures through the Battery Street Tunnel are likely to begin mid-2009.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering July 1, 2003 November 15, 2005 Nickel Funding Began July 1, 2003
Project Definition Complete June 02, 2007 May 18, 2007  
Environmental Document Complete June 02, 2008  Published Supplemental Draft EIS July 23, 2006.
Right of Way Certification November 24, 2009  
Advertisement Date December 07, 2009  
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 294 12.4%
Right-of-Way 336 14.1%
Construction 1750 73.5%
Funded Project Costs 2380 100%

Nickel funds included in above costs

177 7.4%

2005 Transportation Partnership Account

2000 84%

  For more information, go to www.wsdot.wa.gov/projects