|
Recent Progress
There are currently five alternatives under consideration. They are being analyzed to complete the Draft Environmental Impact Statement (DEIS), which has an expected public release date of April 2004. For a description of the alternatives, please visit the project web site at: http://www.wsdot.wa.gov/projects/Viaduct/
The 60 day DEIS public review comment period will conclude on June 1st, 2004. Work continues toward identifying data needed to pick the preferred alternative. To date this effort has centered on ways of reducing the project cost and major construction duration. One right of way parcel has been acquired during this quarter, with one additional parcel currently in negotiations. An additional parcel near Railroad Way S. is being considered for early acquisition. The legislature approved WSDOT request to move $10 million from 03-05 RW to 03-05 PE to allow the project design to move forward as planned. The project team is proposing to advance $28 million PE from the 11-13 biennium to the 05-07 biennium to maintain the design pace to meet an anticipated 2008 construction start.
|