SR 99 - Alaskan Way Viaduct and Seawall Replacement

Quarterly Project Report Update for Quarter Ending June 2004

Project Title & Location

SR 99 - Alaskan Way Viaduct and Seawall Replacement Project - Environmental Impact Statement/Right of Way/Design

Project Description
The existing seismically vulnerable Alaskan Way Viaduct and Seawall are both at the end of their useful life and at risk of sudden and catastrophic failure in an earthquake. The cost to replace in-kind this seismically vulnerable structure is between $2.0 and $2.4 billion. (This figure does not include the cost of replacing the seawall or work north of Battery Street tunnel. Necessary to protect public safety and maintain the transportation corridor.

Contractor/Consultant
Parsons Brinckerhoff Quade & Douglas is the prime design consultant.

Recent Progress
The Draft Environmental Impact Statement (DEIS), which compared the five alternatives under consideration,  was released on March 31, 2004.  For a description of the five alternatives, please visit the project web site at: www.wsdot.wa.gov/projects/Viaduct/ .  The 60 day DEIS public review comment period concluded on June 1, 2004.  Work continues toward identifying data needed to pick the preferred alternative.  This work has centered on the south end configuration, stormwater management approach, and construction traffic approach.

Design Construction Impacts

Further delay in selection of the preferred alternative will continue to delay the Final Environmental Impact Statement and Record of Decision.

Environmental Impacts / Compliance

The DEIS public comments are being collated and categorized, and responses are being prepared for inclusion into the Final Environmental Impact Statement. 

Impacts to Traffic
During early preliminary engineering,  construction contract packages and staging will be studied, and traffic detour strategies will be investigated. 

Project Milestones Scheduled Attained Milestone Outlook
Start Project June 2001 June 2001 Nickel funding began July 1, 2003.
Draft Environmental Document Spring 2004  March 2004 Completed on time and on budget.
Right of Way (early) June 2005 One parcel acquired December 2003.  Additional parcels may be acquired by June 2005.
 Determination of Preferred Alternative  Late Summer 2004   Note: This is a Partnership Project.  The preferred alternative will be a joint decision between WSDOT, City of Seattle and FHWA.
Record of Decision July 2006
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 172.6 85.2%
Right-of-Way 30.0 14.8%
Construction 0.0 0.0%
Funded Project Costs 202.6 100.0%

Nickel funds included in above costs

177.0 87.4%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Alec Williamson, WSDOT Project Engineer @ (206) 382-6366 Or E-mail: viaduct@wsdot.wa.gov