SR 99 - Alaskan Way Viaduct and Seawall Replacement

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location

SR 99 - Alaskan Way Viaduct and Seawall Replacement Project

Project Description
The existing seismically vulnerable Alaskan Way Viaduct and Seawall are both at the end of their useful life and at risk of sudden and catastrophic failure in an earthquake. The cost to replace in-kind this seismically vulnerable structure is between $2.0 and $2.4 billion. (This figure does not include the cost of replacing the seawall or work north of Battery Street tunnel. Necessary to protect public safety and maintain the transportation corridor.

Contractor/Consultant
PB Americas is the prime design consultant. Hatch Mott MacDonald is the Program Management Assistant Consultant

Recent Progress
The team completed the design of electrical relocation and mapping along Western Avenue to support the first utility relocation contract.  Work continues on the Construction Traffic Management Plan.  Initiated the Collaborative Team whose primary directive is to define the design concept for Central Waterfront.

Design Construction Impacts
Design is approaching 100% complete for the Electrical Relocations - Phase 1 Project.  Design to the 30% level is otherwise commencing across the Program.  Major Roadway construction is planned to begin Winter 2009.

Environmental Impacts / Compliance
Program Environmental staff continues to work on the environmental assessment documents for the "Moving Foward" Projects.

Impacts to Traffic
Utilities construction, currently scheduled to begin Summer 2008, will impact traffic on local city streets.  Night and weekend lane closures through the Battery Street Tunnel are likely to begin mid-2009.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering July 1, 2003 July 1, 2003 Nickel Funding Began July 1, 2003
Project Definition Complete June 02, 2007 May 18, 2007  
Environmental Document Complete June 02, 2008  Published Supplemental Draft EIS July 23, 2006.
Right of Way Certification November 24, 2009  
Advertisement Date December 07, 2009  
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 294 12.2%
Right-of-Way 314 13.1%
Construction 1793 74.7%
Funded Project Costs 2401 100%

Nickel funds included in above costs

265 11%

2005 Transportation Partnership Account

1613 67.2%

  For more information, go to www.wsdot.wa.gov/projects