SR 99 - Alaskan Way Viaduct and Seawall Replacement

Quarterly Project Report Update for Quarter Ending June 2003

Project Title & Location

SR 99 - Alaskan Way Viaduct - Seattle Seawall Replacement Project - Environmental impact statement/Right of Way/Design

Project Description
The existing seismically vulnerable Alaskan Way Viaduct and Seawall are both at the end of their useful life and at risk of sudden and catastrophic failure in an earthquake. The cost to replace in-kind this seismically vulnerable structure is between $2.0 and $2.4 billion. (This figure does not include the cost of replacing the seawall or work north of Battery Street tunnel. Necessary to protect public safety and maintain the transportation corridor.

Contractor/Consultant
Parsons Brinckerhoff Quade & Douglas is the prime design consultant.

Recent Progress
Nickel funding begins July 1, 2003.  Refinements of scope and costs for project alternatives were completed in June 2003.  The selected alternatives are being utilized to complete the Environmental Impact Statement.     For a description of the selected alternatives, please visit the project web site at: http://www.wsdot.wa.gov/projects/Viaduct/

Design Construction Impacts
The recent Cost Estimate Validation Process (CEVPTM) estimates construction durations between 6 and 11 years, depending on the alternative.  Funding for construction depends upon additional funding from the Regional Transportation Investment District (RTID) as well as other new funding.  For a description of the design alternatives and information on the CEVP process please visit the project web site at: http://www.wsdot.wa.gov/projects/Viaduct/

Environmental Impacts / Compliance
Environmental assessment and documentation is underway and on schedule.   Work remains within scope and budget.

Impacts to Traffic
Not yet fully determined; however, impacts will vary significantly with each alternative.

Project Milestones Scheduled Attained Milestone Outlook
Start Project June 2001 June 2001 Nickel funding begins July 1, 2003.
Draft Environmental Document Spring 2004   No issues at this time.
Right of Way (early) June 2005 No issues at this time.
      Note: This is a Partnership Project.  Milestones to be determined with partners.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 172.5 85.2%
Right-of-Way 30.0 14.8%
Construction 0.0 0.0%
Funded Project Costs 202.5 100.0%

Nickel funds included in above costs

177.0 87.4%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Tom Madden, WSDOT Engineering Manager @ (206) 382-8308 Or E-mail: viaduct@wsdot.wa.gov