Project Title & Location
SR 99 - Alaskan Way Viaduct and Seawall Replacement Project
|
Project Description
The existing seismically vulnerable Alaskan Way Viaduct and Seawall are both at the end of their useful life and at risk of sudden and catastrophic failure in an earthquake. The cost to replace in-kind this seismically vulnerable structure is between $2.0 and $2.4 billion. (This figure does not include the cost of replacing the seawall or work north of Battery Street tunnel. Necessary to protect public safety and maintain the transportation corridor.
|
|
Environmental Impacts / Compliance
The Biological Assessment was submitted to USF&W and NMFS on October 13, 2006. The comment period for the SDEIS closed in September 2006. The AWV Project Team is collating and answering comments received. Work has begun on developing a mitigation strategy for the final EIS.
|
Impacts to Traffic
The team continues to analyze the trade offs between construction duration, cost, and maintenance of traffic, and impact to the community.
|