SR 99 and SR 520 Materials and Publications - Updated Cost Estimates

Materials & Publications

WSDOT Response to the Expert Review Panel Recommendations

On September 20, 2006 WSDOT presented revised cost estimates for the SR 99 Alaskan Way Viaduct and Seawall Replacement and the SR 520 Bridge Replacement and HOV projects.


Letter from the Governor to WSDOT

On September 1, 2006 the Governor requested that WSDOT review Expert Review Panel's final report and re-evaluate the cost estimates.

Letter from the Governor to the Expert Review Panel

On September 1, 2006 the Governor requested the Expert Review Panel provide additional advice.  

Expert Review Panel Report

On August 31, 2006 the Expert Review Panel released their Final Report:

For more information on the Expert Review Panel, visit the website.