Aug. 27 project update: Tunneling machine’s front end bolted in place

Posted on Aug 27 2015 12:01 PM
Seattle Tunnel Partners has reconnected the SR 99 tunneling machine’s 2,000-ton front end to the section that remained in the access pit during repairs. With the two sections of the machine now bolted together, crews from Mammoet have unhooked the front-end piece from the massive red crane that performed this week’s lift.
 
Photos of the lift are available on Flickr, and the time-lapse video below shows the whole thing in 62 seconds.
 
 

What's next?

Significant work remains for crews tasked with reassembling the machine. Three large pieces of the machine’s outer shield will be lowered into place for reassembly in the coming days, according to STP’s most recent schedule. Crews also must weld the pieces back together, in addition to the lengthy task of reconnecting the hundreds of wires and hoses that are integral to the tunneling operation. STP and manufacturer Hitachi Zosen will conduct a series of tests following reassembly to ensure the machine is ready to resume mining.
 
You can track the action on our time-lapse camera and follow @BerthaDigsSR99 on Twitter for updates. We’ll also continue to post photos and videos as STP’s work progresses.