Seattle Tunnel Partners schedule update: Construction of the access pit’s underground walls will continue through August

Posted on Jul 28 2014 9:36 AM

Today, Seattle Tunnel Partners notified us that building the underground walls of the circular pit (pdf 2.5 Mb) crews will use to access and repair the SR 99 tunneling machine will continue through August. While this date is later than anticipated, STP reports that tunneling is still expected to resume as scheduled in March 2015.

Building a self-supporting, concrete ring that is 120 feet deep and 80 feet wide is no easy task, especially given the difficult ground conditions near South Jackson Street. STP crews have completed more than half of the underground piles and are working around-the-clock, seven days a week to complete the approximately 31 remaining piles.

There are several reasons the work is taking longer than anticipated. One factor is the addition of 11 piles to the design, bringing the total number of piles to approximately 84. Crews are also working with exceptionally large interlocking piles, which are necessary to make the pit self-supporting without tiebacks or other reinforcements. A self-supporting pit is what will allow the tunneling machine to mine through its walls, but the large piles take longer to install than standard piles.

While pile work continues, crews are making progress on other areas of the repair plan on schedule, including:

  • Shipping repair pieces: The new main bearing has arrived in Seattle and will be assembled closer to the time it’s needed, likely this fall.
  • Manufacturing repair pieces: Other repair pieces, such as the new outer seal ring, the thrust seal ring and bearing block are nearing completion. After these pieces are fabricated and inspected, Hitachi Zosen will ship them to Seattle.
  • Assembling a 300-ton crawler crane: This crane will be used to help assemble the 600-ton crawler crane. Pieces of that crane will arrive in September and assembly will begin shortly thereafter.
  • Assembling a 600-ton crawler crane: This crane will be used to assemble the modular lift tower (massive red crane) that will lift the largest pieces of the machine from the access pit. Parts of that crane will also arrive in September and assembly will begin in late September.
  • Assembling the 2,000-ton modular lift tower: Starting in late July and continuing through fall, crews will begin to stage the modular lift tower. Parts of the modular lift tower will arrive over the next several months beginning in late July.

 

We will continue to update you on STP’s efforts to resume tunneling by March 2015. You can watch the access pit take shape on our time-lapse camera, and view photos of recent construction on Flickr

Previous updates 

June 16, 2014 update – Contractor announces details of repair work plan for the SR 99 tunneling machine

May 13, 2014 update – Construction of access pit’s underground walls now underway

May 8, 2014 update - With environmental review complete, access pit construction begins in earnest

April 29, 2014 update - A summary of change orders on the SR 99 Tunnel Project

April 21, 2014 update - SR 99 tunneling machine to resume digging in March 2015

Click here to see a full archive of progress updates