US 97 - Satus Creek Bridge - Bridge Replacement

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
US 97 - Satus Creek Bridge - Bridge Replacement

Project Description
This project will replace the Satus Creek Bridge on US 97 south of Toppenish with a new, wider bridge that meets current design standards. Replacing the bridge and realigning this stretch of roadway will improve safety and reduce collisions.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
This project is in the early design stage.  The WSDOT Bridge office is currently working on possible bridge designs.

Design Construction Impacts
A land ownership dispute in the area of the project has delayed the start of the cultural report.  This report is key to the delivery of this project.  Several milestones may be delayed.

Environmental Impacts / Compliance
Cultural and habitat impacts are likely.

Impacts to Traffic
A detour bridge is planned be used.

Project Milestones Scheduled Attained Milestone Outlook
Project Start February 2000 February 2000 Project Started
Environmental Documents Complete March 2007 Impacts are likely.
Right of Way Certified January 2009 Impacts are likely.
Contract Advertisement Date February 2009 Impacts are likely.
Operationally Complete December 2009 Impacts are likely.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 1.4 15.4 %
Right-of-Way $ 0.1  1.1 %
Construction $ 7.6 83.5 %
Funded Project Costs $ 9.1 100 %

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Graph includes $273,000 prior to July 2005 

Troy Suing, WSDOT Project Engineer