US 97 - Brewster - Pedestrian Illumination - Complete December 2008

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
US 97, Brewster Vicinity - Install Lighting

Project Description
US 97, at this location, has inadequate lighting for pedestrians. Install streetlights on US 97 in Brewster. This will reduce nighttime risk to pedestrians.

Contractor/Consultant
J-U-B Engineers is the consultant for the preliminary engineering portion of this project.

Recent Progress
The deisgn team met with the mayor and city council and has held an open house to discuss the project with local residents and business.

Design Construction Impacts
The project will not have right of way impacts but the PEF sidewalk project that is being constructed with this project will have access impacts to businesses adjacent to the highway.

Environmental Impacts / Compliance
Concurance from USFWS has been recieved and a NEPA Documented CE is completed.

Impacts to Traffic
There will be minimal impacts to traffic during construction.

Project Milestones Scheduled Attained Milestone Outlook
Project Definition July 3, 2006 July 3, 2006 Complete
Begin Preliminary Engineering November 23, 2005 November 23, 2005 Complete
Environmental Completion September 15, 2008 No issues at this time.
Ad Date November 3, 2008 No issues at this time.
Operationally Complete November 1, 2009 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering .06 32
Right-of-Way 0
Construction .125 68
Funded Project Costs .185 100

Nickel funds included in above costs

2005 Transportation Partnership Account

.185 100