Project Title & Location
US 97/Blewett Pass - Passing Lane
|
Project Description
|
|
Contractor/Consultant
N/A
|
|
Recent Progress
-Reimbursement agreement with USFS has been signed and executed. -Pre-Biological Assessment meeting wa held on May 21, 2010. -Noise study was completed on April 3, 2009. -Botanical and Cultural survey studies are scheduled in June, 2009. -ARPA permit was signed on May 26, 2009. -Hydraulic report is in the approval process.
|
|
Design Construction Impacts
Due to recent findings of Owl near the project area, the earliest allowed construction start is mid-August, 2010. With 35 working days estimated for construction, paving becomes more critical and dependent on the weather conditions. Ad date revised to 5/3/10 due to formal consultation timeline for spotted owls.
|
|
Environmental Impacts / Compliance
A formal consultation for the Biological Assessment will be required.
|
Impacts to Traffic
No major impact is expected. A one lane closure with two-way traffic will be utilized.
|