US 395 - NSC - Spokane River to Francis - Grading

Status

May/June 2017

  • Weekly Construction Update
  • Under construction
  • Awarded to Red Diamond Construction, Inc. of Spokane with a construction bid of $382,482. 

Work will entail curb & sidewalk work on city streets that are immediately adjacent to the NSC right of way.  Drainage work is also included.  Mainline freeway grading is not included at this time.

Why is WSDOT making these improvements?
Following right of way purchases, local streets adjacent to the NSC route need minor improvements.

The End Result
Curb, sidewalks, drainage, and dead end street segments improved.

Project Benefits
Improved esthetics along adjacent streets.

What is the project timeline?
The local street portion of this project should be completed in 2016.  The mainline grading component has been postponed, pending revised desin work.

Financial Information

Financial Data for PIN 600013A
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $1,199
2005 Gas Tax (TPA) $1,331
Pre-Existing Funds (PEF) $0
CWA $0
Total $2,530

Project signage will reflect the cost of construction engineering, project bid award and sales tax.