Project Title & Location
NSC-US 2 to Wandermere & US 2 Lowering - Construct New Roadway
|
Project Description
Constructs four new drivable lanes of the North Spokane Corridor between Farwell Road and Wandermere including a new connection to US 395 at Wandermere. Constructs an interchange at US 2. This project will increase capacity and reduce travel time. There will be four lanes when this project is completed.
|
|
Recent Progress
This project will have two contracts. The PS& E for the first, US 2 Lowering, was advertised on August 18, 2008 with bid opening scheduled for Oct. 2. The PS&E for the second, US 2 to Wandermere is in progress. HQ environmental re-delineated the wetland that may be temporarily impacted by the bridge pier. Continue work on Design, Design Documentation, and PS&E. Geotech still working on foundation recommendations. Exploring the use of the Hatch Road property for borrow material. The use will depend on a facilities contract that may or may not involve the property.
|