Project Title & Location
NSC-US 2 to Wandermere & US 2 Lowering - Construct New Roadway
|
Project Description
Constructs four new drivable lanes of the North Spokane Corridor between Farwell Road and Wandermere including a new connection to US 395 at Wandermere. Constructs an interchange at US 2. This project will increase capacity and reduce travel time. There will be four lanes when this project is completed.
|
|
Recent Progress
This project will have two contracts. The PS& E for the first, US 2 Lowering, is approximately 45% complete. The PS&E for the second, US 2 to Wandermere is approximately 25% complete. Work on this project has increased recently due to completion of the Francis Avenue to Farwell Road Project. Ongoing work in the Project Office includes investigating alternative retaining wall and Deadman Creek crossing designs, continuing hydraulic design, finalizing the US 2 interchange plans for approval, continuing staging plan design, designing frontage roads, traffic analysis and preparing preliminary contract plan sheets.
|